Features

This material is produced by the Monterey Institute's Center for Nonproliferation Studies
What's New in the Database
Armenia
Export Controls
Export Control Developments
Metsamor Nuclear Power Plant
Nuclear Research Facilities
Nuclear-Related Government Agencies
Russian-Armenian Agreement on the Peaceful Use of Nuclear Power
Other Countries  
Topic Index
Search
Glossary
Maps
Tables


This is an archived page. Please visit the new Armenia country profile at http://www.nti.org/e_research/profiles/Armenia/index.html.
Armenia: Reopening Metsamor

By Kseniya Yershova and Mary Wells

October 1996
Revised April 1997

In the 1960s, the Soviet leadership decided to meet the growing energy needs of the copper and aluminum production industry in Armenia by building a nuclear power plant.[1] Unit 1, a VVER reactor that did not possess a seismic resistance system, became operational in 1976. Unit 2, which went on-line in 1979, was designed to withstand an earthquake registering up to 8 on the Richter scale.[2]

In the 1980s, a strong environmentalist movement developed in Armenia under the leadership of Hachik Stamultyan. The movement successfully campaigned to close several environmentally hazardous manufacturing facilities and insisted on shutting down the Metsamor nuclear power plant.[3] In September 1988, the Armenian government promised to close the plant by 1991. The devastating 7 December 1988 earthquake, followed by an order from the Central Committee of the Communist Party, finalized the decision to shut the reactors down, although the reactors themselves were undamaged by the quake. Unit 1 was shut down on 25 February 1989, and Unit 2 on 18 March 1989.

SHUT DOWN / UNIT 2 RESTART

The closure of Metsamor in 1989 forced Armenia to depend on neighboring states for energy due to its lack of sufficient indigenous energy resources. In 1991, pressure to restart the plant grew after a vital natural gas pipeline from Turkmenistan was cut off by a Turkish and Azerbaijani-led fuel embargo as punishment for the civil war in Nagorno-Karabakh. Advocates of reactivation argued that Armenia did not have any alternative to meet its energy needs and that the safety of the reactor and the plant in general could be ensured. In November 1992, Armenian authorities indicated their intention to restart Unit 2 with the goal of recomissioning it by early 1993.[4] On 18 March 1993 the Armenian parliament convened an emergency session on solving the energy crisis, revoked its own decree requiring a national referendum to decide upon the restart of the NPP, and gave the decision-making authority to the executive branch.[5] Taking into consideration the improved design of Unit 2, the Armenian government decided in April 1993 to recommission it.[2] IAEA officials visited Metsamor from 27-30 August 1993 and found no technical reasons not to restart the plant. [6] IAEA Director General Hans Blix also visited Metsamor in 12/93 and promised IAEA assistance in restarting the plant, as well as help in securing EBRD assistance. [7] 

OPPOSITION & COST

Among the arguments against the reopening of the plant were the age of the VVER-440 design, which some felt was not worth restoring; the seismic instability of the region; weak nuclear regulatory authority; and regional conflict. Azerbaijan, Georgia, and Turkey protested the reopening of the plant, largely on political grounds. The West was for the most part, adamantly opposed to restarting Metsamor, and Armenia was ineligible for international assistance, such as aid distributed throughout the Nuclear Safety Account of the EBRD.[8] As far back as January 1992, Western experts worried that Armenia would not have enough money to refit the reactor safely, and would risk operating it in dangerous and politically unstable conditions.[9] The United States voiced its strong reservations about financing the "dangerous" reactor; in one instance it denied Armenia aid for upgrading the plant since the reactor lacked a containment vessel to prevent the accidental release of radiation.[10] In addition, the cost of recommissioning the Metsamor plant was estimated to be between $80 and $200 million. In August 1992, the Armenian government began seeking $100 to $150 million in western loans.[4] 

FOREIGN ASSISTANCE

In autumn 1992, officials from the Russian Ministry of Atomic Energy gave their support to the restart proposal of Unit 2, conditioned upon the cessation of fighting in the Nagorno-Karabakh region.[4] In February 1994, Armenian Prime Minister Grant Bagratyan and Russian Deputy Prime Minister Oleg Soskevets reached an agreement under which Russia would provide equipment and specialists for the plant.[11] Later in March 1994, Russia agreed to provide technical assistance and nuclear fuel, as well as to monitor safety operations. In return, Armenia promised not to use nuclear fuel or the reactor for military purposes nor to transfer nuclear material to a third country.[1] The Armenian firm Atomtekhenergo was chosen to develop a restoration and recommissioning program, while the Kurchatov Institute, Atomteploenergoproekt, and Gidropress, all from Russia, were responsible for project management and design, and construction.[12] Equipment for the plant was supplied by at least 70 Russian enterprises; other reports indicate of the 193 contracts signed, over half were with Russian companies.[13] On 10 October 1994, Russia and Armenia signed an agreement on a 110 billion ruble loan, of which 60 million was spent on reopening Metsamor.[14] (The agreement was ratified in January 1995.) In addition, Russia provided training programs for Metsamor operators at the Novovoronezh and Kola nuclear power plants in Russia, which use the same VVER-type power reactors. Metsamor nuclear plant employees, seventy-five percent of whom had previous NPP experience, also received training at Greifswald, Germany and Loviisa, Finland.[15,16] In 1994-1995, international aid increased. Armenian expatriates contributed $35 million in the form of loans and donations for the recommissioning.[14] In 12/94, Russia loaned 20 billion rubles for radiation monitoring and other restart projects.[17] (Another report claims that Russia loaned 60 billion rubles for modernization and restart activities.)[18] Finally, in March 1995, Ukraine agreed to help train personnel.[15] By April 1995, it was reported that approximately $70 million had been spent on rehabilitating the facility.[19] (However, another report stated that only $48 million was spent on rehabilitating the facility, $10 million of which were loans from Russia.)[1] During 1994-95, Armenia's critical energy shortages may have suggested an immediate recommissioning of Metsamor, but safety was the higher priority. 

SAFETY & RECOMMISSIONING

For eighteen months in 1994-95, every piece of equipment was thoroughly inspected.[16] During that period, more than 500 tons of equipment were airlifted (to avoid Azerbaijani roadblocks) to the plant and more than 800 upgrades were carried out.[8]

In July 1994, the IAEA concluded that "the plant is safe and there are no principle obstacles for restart."[2] However, in March 1995, EBRD officials refused to conduct a scheduled inspection, as it did not consider the plant to meet safety standards; it instead offered to loan Armenia funds to build a fossil-fueled power plant.[20] Also in March 1995, it was reported that despite Armgosatomnadzor's (Armenian Nuclear Regulatory Body) approval of upgrades to the primary circuit; protection and control systems; thermal insulation; emergency cooling systems; and fire and explosion protection systems, some IAEA officials had reservations about the safety of the plant’s pressure vessel annealment and seismic resistance.[21] Nevertheless, Armenian officials continued with plans to restart Metsamor-2. In May 1995, Armen Abagyan, director of the All-Russian Institute of Nuclear Power Plant Operations, said that six planeloads of nuclear fuel worth $22 million were shipped to Metsamor.[22] Later that month, the Russian company Rosatomenergo approved the plant for recommissioning.[23] Officials reopened the Metsamor plant in June 1995, conducted a low power criticality test in October 1995, and on 26 October 1995 Unit 2 went critical.[24, 25, 26] At 5:30 p.m. on 5 November 1995, Unit 2 began producing electricity for the first time since 1989, at an initial output of 20% capacity, or 80 MWe.[27] 

SAFETY DEBATE

Even after the reopening of Metsamor, the debate over the expediency of the decision continued. On the one hand, Russian Prime Minister Viktor Chernomyrdin stated in his address to Armenian President Levon Ter-Petrosyan that Russia would continue to assist Armenia in ensuring safe and continuous operation of the Metsamor nuclear power plant. [28] On the other hand, intellectuals including A. Abramyan, a doctor of technological sciences, protested against the "insane" decision, arguing that nuclear fuel and maintenance costs, along with the probability of an accident, outweighed any possible advantages Armenia might gain by having its own nuclear power plant.[29] In addition, Akop Sanasaryan, head of the Green Union of Armenia, claimed that the Metsamor plant did not meet internationally accepted nuclear safety standards, due to the lack of a containment vessel.[20] Georgia, Turkey, and Azerbaijan also expressed concern over the lack of a containment vessel.[30] Such a containment vessel would protect the core from a mortar attack, but the conventional wisdom in Yerevan is that any attack would come from a close neighbor rather than from a distance, so the possibility of radiation escape serves as a deterrent to such attacks. Metsamor's proximity to an airport and its use as a guidance landmark is concern for some that it could be hit by falling aircraft. [16] Nevertheless, during an official visit to Armenia in November 1995, Russian Minister of Atomic Energy Victor Mikhailov said that the level of reliability and safety at the re-opened Metsamor nuclear power plant was adequate. [31] 

UNIT 1 RESTART

In November 1995, the Russian Ministry of Atomic Energy and the Armenian Ministry of Energy signed an agreement on the recommissioning of Unit 1, which Armenia plans to overhaul in 1996-1997.[32,15] Armenia plans to invest $80 million into the energy sector over 1996-1997 period, of which $5 million will be spent annually on safety improvements. [1]

Sources:
[1] Ara Tatevosyan, "Living Dangerously with Nuclear Power in Armenia," Transition, 3 May 1996, pp. 23-25, 63.
[2] Robert Ebel, James Schlesinger, "Energy and Nuclear Power in Armenia," in Nuclear Energy Safety in the Former Soviet Union, (The Center for Strategic and International Studies, Washington, DC, 1995, pp. 57-64); World Nuclear Industry Handbook, 1992, p. 55.
[3] Interview with Armenian government official, July 1995, Monterey, California.
[4] William Potter, "The Future of Nuclear Power and Nuclear Safety in the Former Soviet Union," Nuclear News, March 1993, pp. 61-67.
[5] Pravda, 30 March 1993, p. 4.
[6] IAEA Bulletin, February 1993, p. 51.
[7] Mayak Radio Network (Moscow), 14 December 1993, in FBIS-SOV-93-239, 15 December 1993, pp. 97-98.
[8] Astghik Vardanian, "Armenia's Choice," Bulletin of the Atomic Scientists, July/August, 1996, pp. 50-54
[9] "Armenia Wants Western Help At Nuclear Power Plant," Reuter, 25 August 1992.
[10] "Despite U.S. Protests, Armenia Will Restart Nuclear Reactor," New York Times, 24 October 1995, p. A4.
[11] Liz Fuller, "Russia To Help Reactivate Armenian Nuclear Power Station," RFE/RL News Briefs, 14 February 1994, p. 9.
[12] Interfax, 13 April 1993; in "Armenia: Government to Begin Work to Repair Nuclear Power Plant," JPRS-TEN-93-013, 14 May 1993, p. 23 and Interfax, 14 April 1993; in "Armenia: Government Budgets 5 Billion Rubles for Nuclear Plant," JPRS-TEN-93-013, 14 May 1993, p. 24.
[13] Liana Minasyan, "Nuclear Station Will Operate," Nezavisimaya Gazeta, 12 May 1995, p. 2; in FBIS-SOV-95-102-S, 12 May 1995.
[14] Liz Fuller, "Russian Credits For Armenia," RFE/RL Daily Report, 11 October 1994; "Power Reactor Restart On The Horizon," Nuclear News, December 1994, p. 39; "Russians Give Credit To Armenian Restart," Nuclear Engineering International, November 1994, p. 6; "Armenia," Nuexco Review, 1994, p. 50.
[15] "Russia Gave Armenia A Nuclear Power Plant," VEK, No. 44 (161), 1995, p. 6; Source Book: Soviet Designed Nuclear Power Plants in Russia, Ukraine, Lithuania, Armenia, the Czech Republic, the Slovak Republic, Hungary and Bulgaria, 4th edition, Nuclear Energy Institute, Washington DC, 1996, p. 202; "Nuclear Returns To Energy-Starved Armenia," Nuclear Europe Worldscan, January-February 1996, p. 50.
[16] Richard Wilson, "Report on the Restart of the Medzamor Nuclear Power Plant in the Republic of Armenia," Andrei Sakharov Foundation, 25 July 1995, http://www.wdn.com/asf/armnp.html. {entered 11/20/96 djw}
[17] Yerevan Lgarir Daily, 9 December 1994; in "Reconstruction To Continue At Nuclear Power Plan," FBIS-SOV-94, 9 December 1994.
[18] "New Reactors and Restarts," Nuexco Review, 1/95, p. 11.
[19] Aragil Electronic News Bulletin, 30 April 1995; in "Prime Minister On Operation Of Nuclear Power Plan," FBIS-SOV-95-083, 30 April 1995; "June-July Restart Planned for Two-Unit VVER Plant," Nuclear News, March 1995, p. 46; "New Reactors And Restarts," Nuexco Review, January 1995, p. 11.
[20] "Armenia," Yadernyy Kontrol, March 1995, No. 3, p. 9, 13.
[21] "Armenian Plant Restart Worries IAEA Experts," Nucleonics Week, 23 March 1995, p. 15.
[22] "Armenian Plans For Medzamor-2 On Schedule For Restart This Year," Nucleonics Week, 4 May 1995, p. 6.
[23] Interfax (Moscow), 27 May 1995; in JPRS-TEN-95-008, 27 May 1995.
[24] Nucleonics Week, 2 November 1995, p. 15; "Armenian Nuclear Power Plant Is Not Afraid of Earthquakes: At Night Reactor Went Critical," Izvestiya, 28 October 1995, p. 1.
[25] "Armenia", Current Digest, 22 November 1995, p. 20.
[26] Margaret Ryan, "Armenia On Verge Of Restarting Medzamor-2 To Meet Winter Need," Nucleonics Week, 26 October 1995, pp. 2-3; "In Armenia," Post-Soviet Nuclear and Defense Monitor, 17 November 1995, p. 16.
[27] NucNet News, 8 November 1995, 508/95; Interfax, 6 November 1995; in FBIS-SOV-95-215, "Second Reactor at Armyanskaya AES Working on Schedule," 7 November 1995.
[28] ITAR-TASS (Moscow), 27 June 1995; in "Chernomyrdin Message to Armenia on Nuclear Plant," FBIS-SOV-95-124, 27 June 1995.
[29] Golos Armenii (Yerevan), 10 June 1995, p. 1; in "Scientists Condemn Planned AES Restart," FBIS-SOV-95-122-S, 10 June 1995.
[30] Washington Post, "Armenia Restarts Nuclear Plant," 28 June 1995; see also Segodnya, "Nuclear Power Plant Will Be Restarted Only After Safety Guarantees Are Applied," 2 June 1995, p. 8.
[31] Yerevan Armenia's Radio First Program Network, 7 November 1995; in FBIS-SOV-95-216, "Russian Atomic Energy Minister Arrives, Says Plant Safe," 7 November 1995.
[32] "Armenia-2 Restarts After Six-Year Shutdown," Nuclear News, December 1995.

Comments or questions? Contact Kenley Butler at MIIS CNS: Kenley.Butler@miis.edu

 

CNSThis material is produced independently for NTI by the Center for Nonproliferation Studies at the Monterey Institute of International Studies and does not necessarily reflect the opinions of and has not been independently verified by NTI or its directors, officers, employees, agents. Copyright © 2002 by MIIS.

HOME  |  CONTACT US  |  SITE MAP

















 

Armenia: Reopening Metsamor