![]() |
![]() |
![]() |
|||
![]() ![]() ![]() ![]() |
|||||
|
![]() |
|
|||||||||||||||||||||||||||||||||||||||||
|
by Lisa Holtyn, CNS Graduate Research Assistant
INTRODUCTIONIn response to what is often referred to as the "Chernobyl syndrome," a
public backlash against nuclear power in the wake of the Chernobyl accident
in 1986, the Rostov Oblast Council decided to suspend construction of the
Rostov NPP in 1990.[1] This decision was supported by a parallel
decree by the Russian republican government, and in 1992, the oblast council
voted to permanently ban any further construction of the power plant.[2]
However, in 1996 Minatom announced plans to resume construction of the
Rostov NPP due to a severe energy shortage in the region.[3] This
announcement led to major protest actions on the part of environmental
groups and other concerned parties. The decision to resume construction
has been so controversial and caused such an uproar that it led to three
separate hostile confrontations in the summer of
1997 between environmental activists and nuclear power plant workers,
in addition to numerous town meetings, appeals to the regional legislative
assembly, and even national-level debate.
FACTORS INFLUENCING DECISION TO RESUME CONSTRUCTIONMinatom's decision to resume construction of the Rostov NPP was based primarily upon a severe shortage of electric power in the region, which produces between only one quarter[4] and one third[5] of the energy it consumes. As the rest must be imported, the cost per kilowatt hour is over three times as expensive for industrial and agricultural enterprises than it would be if it were generated locally. The commissioning of the first and second reactors (in 1998 and 2000, respectively) would provide the region with 2,000 additional megawatts of output, and the resulting lower prices would enable the region to emerge from its current economic stagnation.[5] At the time that the NPP was mothballed, the first reactor was over 95 percent complete, and the second reactor was 47 percent complete. Over $800 million has already been invested in construction of the plant, and another $300 million is needed to complete the first reactor.[1] According to then-Minister of Atomic Energy Viktor Mikhailov, Minatom will invest $100 million to start up the first reactor, and the remaining $200 million will come from domestic banks and the French company Electricite de France.[1,4] Minatom will also invest an additional $600 million for completion of the second reactor.[4] Original plans called for the completion of four reactors;[6] however, two reactors are sufficient for the region's energy needs until the year 2000, and will allow for the decommissioning of two aging non-nuclear power plants in the area.[7] Because of worn-out equipment in currently operating plants, it is possible that electricity output will drop by 1000 megawatts within the next seven years. Without alternative energy sources such as the Rostov NPP, the electricity deficit in the region will reach 1,500 megawatts.[8] Another factor that influenced the decision
to resume construction was the financial burden that Minatom must bear
in order to preserve the mothballed NPP. Minatom employs over 1,200
people at the plant,[9] and costs more than R80 billion yearly just
to maintain in its current non-operational status.[4] Mikhailov stated
that this financial burden would be passed on to the regional government
if the oblast legislative assembly voted against finishing construction
of the plant.[8]
CRITICISMS OF ROSTOV NPPThe Rostov NPP has been the object not only of public opposition, but of severe criticism from many leading environmental experts who cite numerous problems related to its location and construction, which violate strict post-Chernobyl laws. Criticisms include the following:
PLANT PROPONENT COUNTER-ARGUMENTSProponents of the plant argue that it will in fact meet with the new safety standards implemented since Chernobyl and will not pose a threat to the environment or public health. The Russian Federation State Committee on the Environment (then-Ministry of the Environment), which assessed the potential risks posed by the NPP in response to the renewed controversy, concluded that the plant was environmentally safe. According to the opinion of some experts, the reactors are supposedly capable of withstanding a 7-point earthquake, and they are even designed to withstand the blow of a 20 metric ton airplane crashing directly into the plant at the speed of 720 kilometers per hour.[1,8] Regarding potential contamination of the water supply, the projected estimates of radiation which would be released through normal operation of the reactors is tens of thousands of times lower than the level necessary to cause some type of disturbance in the ecosystem.[8] PUBLIC ACTION AGAINST ROSTOV NPPSince the announcement by Minatom to resume construction in 1996, there have been continuous attempts by various parties to prevent the plans from going forward. Opponents of the NPP say that, contrary to the claims of Minatom, none of the major issues which prompted the initial decision in 1990 to mothball the plant have been resolved. According to one radio report from 4 December 1997, only 20 out of 46 experts on a commission tasked with determining the environmental impact of the NPP actually endorsed the project ( it is unclear whether or not the commission referred to in this report is the same body as the Russian Federation State Committee on the Environment).[2] This unabated concern over the potential threat posed by the NPP has led to protest actions by numerous national and international environmental groups, and even resulted in hostile confrontations with NPP workers on at least three separate occasions:
In addition to such protest actions, there have been a number of appeals by various groups to the Volgodonsk city and Rostov Oblast councils demanding that a public referendum be held to determine the fate of the NPP. Although the Volgodonsk city council passed a resolution demanding a local referendum,[1] the oblast council has thus far not consented, even though it has received formal requests for a referendum not only from city and regional councils, but also from environmental groups, the administration of the oblast, and even the Russian Federation State Committee on the Environment, which had already concluded that the plant was not a threat to the environment.[19] According to some sources, Minatom can not legally resume construction without obtaining the prior consent of the Rostov oblast legislative assembly, which must first revoke the oblast's Soviet-era decree that banned further construction in 1990.[2,4] However, according to Alexander Zharkov, head of the department of nuclear safety of the Rostov NPP, since the NPP is a federal structure and therefore under federal jurisdiction, the lack of consent by the oblast legislative assembly cannot legally impede the federal government's decision to re-start the NPP. According to Mr. Zharkov, all necessary approval at the local level was already given during the original voting on site selection and construction plans, and according to local and federal law it is also only during this stage that a public referendum can be held.[20] As the official findings on the potential impact of the NPP to the environment were completely rejected by numerous environmental groups, Minatom sponsored an environmental conference on 17-18 November 1997 in an attempt to diffuse the opposition. However, opponents of the plant accused the plant's supporters of pursuing their own self-interests, and the conference only served as a venue for more heated exchange on both sides.[2] The issue even reached the federal level when on 2 December 1997 the committee on industry, construction, transportation and energy of the State Duma held a round table discussion to deal with the problems surrounding completion of the Rostov nuclear power plant. In spite of the ongoing controversy, the committee recommended that the oblast legislative assembly adopt legislation as quickly as possible to complete construction of the Rostov NPP.[7] On 6 April 1998, the Volgodonsk city legislative assembly finally almost unanimously approved a measure to resume construction of the NPP.[21] At this time, it is unclear whether or not the Rostov oblast legislative assembly has also voted on the issue. However, it appears that the fate of the NPP is still uncertain, as the legality of the conclusions reached by the State Committee on the Environment, which violate a number of active Russian laws, has been questioned by the general prosecutor's office.[19] In January 1998, Greenpeace Russia brought formal charges against the State Committee on the Environment regarding these conclusions, and a trial is set to begin in Moscow in July 1998.[22] Sources: [1] Aleksandr Bezmenov, "Prizrak Rostovskoy atomnoy snova
pugayet ekologov," Kommersant, 6 June 1997, p. 5.
Comments or questions? E-mail Cristina Chuen at MIIS
CNS: Cristina.ChuenATmiis.edu
HOME | CONTACT US | SITE MAP |
|||||||||||||||||||||||||||||||||||||||||||