 |
Russia: Reactors: Power: New Power: South Urals (Yuzhnouralskaya)

-
This file is no longer being updated. For information on
developments in the nuclear power industry, please see the
Nuclear
Power Developments section.
-
LOCATION: Ozersk, Chelyabinsk
Oblast (location of Mayak Production Association)
-
[International Nuclear Safety Center
Database, http://www.ra.anl.gov/INSP/maps/location.]
-
ADMINISTRATION:
-
Director: Vladimir Morozov
-
[Sergey Blinovskikh, "Atomnoy stantsii
- 'da'?" Chelyabinskiy rabochiy, 29 January 2000; in Natsionalnaya
sluzhba novostey, http://nel.nns.ru.]{Entered 4/28/2000 CC}
-
TYPE: Sodium-cooled BN-800 fast
breeder reactor (FBR). To view diagrams of BN-800 reactor systems, click
here.
-
["Fast Reactor Database: Specification
Database," http://frdb.ippe.rssi.ru/database/database.html] {Entered 6/4/99
LBN}
-
UNITS: Two, planned
-
["Nayti investora," Yadernaya bezopasnost,
November-December
1998, No. 18-19, p. 15.] {Entered 5/12/99 LBB}
-
POWER: 800MWe, 2100MWt (nominal
capacity)
-
["Fast Reactor Database: Specification
Database," http://frdb.ippe.rssi.ru/database/database.html] {Entered 6/4/99
LBN}
-
FUEL: MOX
fuel.
-
According to the IAEA's
Fast Reactor Database (based on IAEA-TECDOC-866), when fully loaded,
the reactor core will contain 30kg of U-235 and 1870kg of Pu-239.
-
["Fast Reactor Database: Specification
Database," http://frdb.ippe.rssi.ru/database/database.html] {Entered 6/4/99
LBN}
-
CURRENT STATUS:
-
In November 1998, Gosatomnadzor issued a license
for the construction of the South Urals NPP.[1] Although the license
provides for construction of two reactors, (for more details, see the 12/98
entry below), the original plans for the South Urals NPP called for the
construction of three BN-800 reactors.[2] Construction of
Units 1 and 2 was originally scheduled to be completed by 2000, with construction
of Unit 3 to be completed after 2000.[5] Work began in 1984, but
stopped due to funding problems.[2,3] When construction was stopped in
1987, only concrete foundations for two reactors had been laid.[4] Construction
of the plant was suspended, but not officially stopped, after a local referendum.[6]
Completion of Units 1 and 2, along with construction of Unit 3, became
conditional upon the consent of the local administration and a positive
environmental impact study.[7] In October 1993, it was reported that
the local council in Chelyabinsk Oblast had approved the construction of
the nuclear power plant, and completion of the three reactors was slated
for 2005.[8] As of January 2000, an estimated $1.5 billion would be required
to complete the project. According to Director Vladimir Morozov,
if the government provided half that sum, investors could provide the rest.
Vyacheslav Seredkin, Chief Engineer of the Chelyabinsk power company Chelyabenergo,
says that while the project is not profitable, Chelyabinsk Oblast does
not have enough coal or gas and will eventually turn to nuclear power.
Environmental groups, such as Chelyabinsk's
Movement
for Nuclear Safety, continue to fight against the reactor, noting that
the project has not passed an environmental review.[9] In April 2000 the
South Ural NPP project was included in Minatom's plans for projects to
be realized by 2010. In a visit to Chelyabinsk, Deputy
Minister of Atomic Energy Bulat Nigmatulin said that construction would
begin in 2005 at the earliest.[10]
-
Sources:
-
[1] "Nayti investora," Yadernaya
bezopasnost,
November-December 1998, No. 18-19, p. 15.
{Entered 6/4/99 LBN}
-
[2] Valeriy Bogdan, Victor Murogov,
Vladimir Kagramanyan, Mikhail Troyanov, "Ispolzovaniye plutoniya v Rossii,"
Yadernyy
Kontrol, 11/95, pp. 13-17.
-
[3] Oleg Bukharin, Yadernyy toplivnyy
tsikl v byvshem SSSR i v Rossii: Struktura, vozmozhnosti, perspektivi
(Moscow: Association for Cooperation in Nonproliferation, September 1993),
p. 21.
-
[4] Nils Bohmer and Thomas Nilsen,
"Reprocessing Plants in Siberia: Ozersk," online version located at http://www.ngo.grida.no/ngo/.../sibir/sibir1.htm#O2,
12 April 1996.
-
[5] Ann MacLachlan, "Russia Okays Plan
To Proceed With Major Nuclear Construction," Nucleonics Week, 21
January 1993, pp. 1, 12-13.
-
[6] Natalya Mironova, "Yuzhnouralskaya
NPP--A Chronicle of 1992," Soceco Agency Newsletter, No. 41-b, 15
November 1992, pp. 1-10.
-
[7] Komsomolskaya pravda, 26
January 1993, p. 3.
-
[8] Russian Ministry of Atomic Power;
in "New Russian N-Plant Project Clears First Hurdle," Executive News Service,
8 October 1993.
-
[9] Sergey Blinovskikh, "Atomnoy stantsii
- 'da'?" Chelyabinskiy rabochiy, 29 January 2000; in Natsionalnaya
sluzhba novostey, http://nel.nns.ru.
-
[10] "South-Ural NPP included in Minatom
development plan," Bellona Web Site, http://www.bellona.no.{Updated
4/28/2000 CC}
-
COMMENTS:
-
These reactors are designed to use reactor-grade
plutonium extracted from spent fuel, then gradually switch over to using
their own plutonium.[1] The BN-800 could be used to burn
weapons-grade plutonium stored at the Mayak
facility.[2] According to Victor Murogov, Director of the Institute
of Physics and Power Engineering (IPPE), MOX fuel using weapons-grade
plutonium has been successfully burned in the BR-10, BN-350, and BN-600
reactors.[1] Deputy Minister of Atomic Energy Bulat
Nigmatulin noted in December 1998 that the plant would be environmentally
beneficial for Chelyabinsk Oblast since it could not only burn weapons-grade
plutonium, but also draw water from Mayak's liquid waste ponds, thereby
averting the threat of a radioactive waste overflow.[3]
-
Sources
-
[1] Valeriy Bogdan, Victor Murogov,
Vladimir Kagramanyan, Mikhail Troyanov, "Ispolzovaniye plutoniya v Rossii,"
Yadernyy
Kontrol, 11/95, pp. 13-17.
-
[2] Jack Ashton, "Russians Ready To
Re-Start Big Fast Breeder Project," Nucnet News, 25 May 1994.
-
[3]Sergey Rybak, "Minatom Seeks $1.5-Billion
to Build New Fast Reactor," Nucleonics Week, 24 December 1998, pp.
15-16. {Entered 6/4/99 LBN}
-
-
SOUTH URALS DEVELOPMENTS
(For more recent developments,
see the Nuclear
Power Developments file):
-
-
12/98: CONSTRUCTION
LICENSED, REQUIRES SPONSOR
-
In November 1998, Gosatomnadzor issued
a license to build a new fast breeder reactor power plant at Mayak, according
to Deputy Minister of Atomic Energy Bulat Nigmatulin. He added that
financial problems are the only remaining obstacle to construction of the
South Urals NPP. The new power plant will have two BN-800 fast neutron
reactor units. The estimated cost of each unit is $1.5 billion.
It is expected that it will take six to eight years to build one unit and
an average of $300 million will need to be invested annually. Nigmatulin
said that local authorities support power plant construction since Chelyabinsk
Oblast is experiencing an energy shortage.
-
["Nayti investora," Yadernaya bezopasnost,
November-December
1998, No. 18-19, p. 15.] {Entered 5/12/99 LBB}
-
-
6/6/96: RUSSIA PLANS TO BUILD NEW FAST-BREEDER
REACTOR AT OZERSK
-
Russia plans to build up to three BN-800 fast reactors
at Ozersk. The reactors will be adapted to use plutonium only for fuel
and not to "breed" any additional plutonium, as did previous fast-breeder
reactors in order to produce plutonium for nuclear bombs. The reactors
are supposed to reduce Russia's plutonium stockpile by using plutonium
from dismantled nuclear warheads and highly radioactive waste stored at
Ozersk. In 1989, a commission of the Soviet Academy of Sciences approved
a new reactor design, although it noted two defects. Environmental experts
at Gosplan opposed the building of new reactors claiming that hydro-geologists
had discovered a geological fault where the first projected unit would
be built. Since 1991, energy shortages and unemployment in the area have
reduced opposition to the project. In 1996, it was estimated that at least
one BN-800 reactor would be built.
-
["The Biggest Fast-Breeder Reactor,"
Foreign Report, 6 June 1996.] {Entered 8/19/96 KD}
-
-
6/96: PLANT CONSTRUCTION TO COST
AT LEAST 65 BILLION RUBLES
-
A government spokesman noted that the
construction of the plant will require a minimum of 65 billion rubles ($12.6
million), so additional sources of funding would be necessary to complement
the 15 billion rubles pledged earlier by the government for this project.
-
[UPI News Briefing 96/26-6.]
-
-
5/15/96: GOVERNMENT TO ALLOCATE
FUNDS TO RESUME CONSTRUCTION
-
The Russian Government will allocate
15 billion rubles this year to resume construction of the Yuzhnouralskaya
plant, said Russian First Deputy Prime Minister Oleg Soskovets on his visit
to Ozersk. He claimed that the ecological situation in the region would
improve after the plant is built. The plant will be situated on land contaminated
with radiation and use radioactive water from Techa River as a cooler for
the turbines' condensers. The reactors will run on plutonium. About 5,000
new jobs will be created in the region as a result of the plant's operation.
-
[Interfax, "Funds Allocated To Resume
Nuclear Plant Construction," FBIS-TEN-96-006, 15 May 1996.]
-
-
10/28/95: RUSSIA TO BUILD
BREEDER REACTOR
-
Russian and Western sources reported
that Minister of Atomic Energy Mikhailov announced Russia will construct
an $800 million fast breeder reactor at Chelyabinsk to burn plutonium from
dismantled nuclear weapons and to recycle nuclear waste from civilian reactors
and nuclear submarines. Construction will start in 1996.
-
["Russia To Build Breeder Reactor To
Burn Plutonium," OMRI Daily Digest, 30 October 1995, p. 2.]
-
-
8/30/95: BREEDER REACTOR
PLANS DELAYED
-
The Russian press has reported that
plans for a plutonium-burning BN-800 reactor at the Mayak Chemical Combine
in the South Urals region have been delayed due to lack of funding.
-
Sources:
-
[1] Penny Morvant, "... And The Urals
Nuclear Legacy," OMRI Daily Digest, 1 September 1995, p. 2.
-
[2] Gennadiy Aleksandrov, "Moscow Is
Planning To Sell Plutonium,"
Segodnya, 26 July 1995, p. 7.
-
-
1/2/95: THREE FAST BREEDER
REACTORS TO BE BUILT IN SOUTH URALS
-
It was reported that Minatom plans
to build three 800 MW fast-breeder reactors here, to be designated the
South Urals NPP. No funding has yet been allocated to the project.
-
[Mark Hibbs, "Physical Protection Reportedly
Eroding At Minatom's 10 'Closed Cities' In Russia," NuclearFuel,
2 January 1995, pp. 13-14.]
-
-
9/93: FAST BREEDER REACTOR
CONSTRUCTION APPROVED BY MINATOM
-
Viktor Murogov, Director of the Institute
for Physics and Power Engineering at Obninsk, reportedly stated that Minatom
has approved the construction of three fast neutron reactors by the Mayak
production association for converting Russia's stockpile of weapons-grade
plutonium. One of the new reactors would use about 2.5 tons of plutonium
per year.
-
[Segodnya, 25 September 1993,
p. 3; in "Weapons Grade Plutonium Energy Program Proposed," JPRS-TND-93-031,
8 October 1993, p. 28.]
Page last updated 8 June 2000
For more recent developments,
see the Nuclear
Power Developments file.
Comments or questions? Contact
Cristina Chuen at MIIS
CNS: Cristina.Chuen@miis.edu
This material is produced independently for NTI
by the Center for Nonproliferation Studies at the
Monterey Institute of International Studies and
does not necessarily reflect the opinions of and has
not been independently verified by NTI or its directors, officers,
employees, agents. Copyright © 2002 by MIIS.
HOME | CONTACT US | SITE MAP
|
 |