Features

This material is produced by the Monterey Institute's Center for Nonproliferation Studies
What's New Ukraine Research, Power & Waste Power Reactors Chornobyl
Chornobyl Summary
Administration
Fuel and Energy Overview
Fuel and Energy Developments
Safety and Contamination
Shutdown Overview
Shutdown / Western Aid Developments
Spent Fuel / Radioactive Waste Developments
Reactor Incidents Table


Ukraine: Fuel and Energy Issues, Power Replacement Alternatives at Chornobyl
This is an archived page. Please visit the new Ukraine country profile

Ukraine: Chornobyl NPP Fuel & Energy Developments

This file is no longer being updated.  For information on developments in the nuclear power industry, please see the Ukraine: General Nuclear Power Developments section.

3/26/97: CHORNOBYL DEPUTY DIRECTOR GENERAL SAYS RESTART OF UNIT 2 UNLIKELY
On 3/26/97, Chornobyl Nuclear Power Plant (ChNPP) Deputy Director-General Vasyl Omelchenko stated that bringing Unit 2 back on line was inadvisable. He said that with the proper financing, materials, staff, and equipment, reactor No. 2 could be restarted no sooner than the second quarter of 1998, at a cost of $150 to $200 million (including $50 million for fuel). Omelchenko pointed out that investing the same sum in fuel for coal and thermal power plants could generate 12.5 billion kW/hrs, nearly twice the power output of Unit 2 before it was shut down. Or, as another alternative, the money could be used to complete the Rivne-4 reactor, obviating the need for foreign funding for its construction.
[UNIAN, 3/26/97; in "Ukraine: Second Reactor at Chernobyl May Not be Reconnected," FBIS-SOV-97-085, 3/26/97.]{Entered 7/2/97 MK} {Cleared 7/14/97 JL}
 
3/25/97: RUSSIA'S TVEL SHIPS NUCLEAR FUEL FOR CHORNOBYL-3
Despite the debt of the Chornobyl Nuclear Power Plant (ChNPP) to TVEL, the Russian concern nevertheless shipped enough nuclear fuel on 25 March 1997 to keep Chornobyl-3 operating for two to three months.[1,4] ChNPP reportedly owes $30 million to Russian nuclear fuel suppliers for past shipments; the plant has received no fuel since July 1996. (The Chornobyl RBMK reactor uses fuel assemblies that are produced only in Russia.) However, ChNPP manager Serhiy Parashin noted that the plant recently paid 20 percent of its debt to Russian firms.[2,3] Due to the reduction in power generating capacity, ChNPP produced only 523 million kW/hr in March, 223.7 million kW/hr short of its target production for the month.[5]
Sources:
[1] Raisa Stetsyura, ITAR-TASS, 3/24/97; in "Russia: Moscow To Supply Fuel for Chernobyl 'in 7-10 Days'," FBIS-SOV-97-083, 3/24/97.
[2] Veronika Romanenkova, ITAR-TASS, 3/25/97; in "Russia: Firm Ships Fuel to Chernobyl Nuclear Plant Despite Debt," FBIS-SOV-97-084, 3/25/97.
[3] Oleg Varfolomeyev, "Ukraine Gets Nuclear Fuel, Stops Oil Terminal Construction," OMRI Daily Digest, Vol. 3, No. 60, 3/26/97.
[4] V. Luhovyk, "Chornobyl Revives," Eastern Economist, 4/7/97, p. 10.
[5] Interfax, 4/7/97; in "Ukraine: Chernobyl Electricity Production One-third Below Target," FBIS-SOV-97-097, 4/7/97.{Entered 7/2/97 MK}{Cleared 7/14/97 JL}

 
3/12/97: UKRAINE REDUCES CHORNOBYL-3 OUTPUT TO HALF CAPACITY
Ukraine reduced Chornobyl-3 to half capacity on 12 March 1997 due to a fuel shortage caused by the failure of the Chornobyl Nuclear Power Plant (ChNPP) management to pay the Russian joint stock company, TVEL, for nuclear fuel shipments. According to the head of Chornobyl's information department, Valeriy Idelson, the power plant owes TVEL $3.5 million for past deliveries -- a problem in part due to consumer debt to ChNPP, which now stands at $108 million.[1] One alternative for fueling Unit 3, proposed by the ChNPP management, includes extracting the 600 partially spent nuclear fuel assemblies located in Unit 2; this plan could reportedly save $30 million in the long term. ChNPP representatives have drafted a document on using Unit 2 fuel and submitted it to Derzhkomatom (the State Committee for the Use of Nuclear Power) and the Ministry for Environmental Protection and Nuclear Safety.[2,3] Financial problems notwithstanding, Ukraine expects a fuel shipment within the month. Otherwise, Unit 3 would have to be stopped.[1,4] According to a representative of the Ministry for Environmental Protection and Nuclear Safety, halting Unit 3 represents an unsafe situation, since a reactor requires a large amount of energy for safety and routine maintenance, even when not in operation. Usually, other units at the site provide the needed energy, but in this case, there are no other operable units.[4]
Sources:
[1] Interfax, 3/13/97; in "Fuel Shortage To Cause Shut Down of Chernobyl Power Unit," FBIS-SOV-97-072, 3/13/97.
[2] UNIAN (Kiev), 3/20/97; in "Ukraine: Chernobyl To Utilize Nuclear Fuel From Ruined Generator," FBIS-SOV-97-079, 3/20/97.
[3]"Fuel Second Time Round," Izvestiya Ukraina, 3/25/97, p. 1; in "Ukraine; Fuel From Closed Chernobyl Unit To Be Used in Third Unit," FBIS-SOV-97-084, 3/25/97.
[4] Raisa Stetsyura, ITAR-TASS, 3/13/97; in "Fuel Shortage Halves Chernobyl Reactor Capacity," FBIS-SOV-97-072, 3/13/97.{Entered 7/2/97 MK}{Cleared 7/14/97 JL}

 
11/30/96: UKRAINE SHUTS DOWN CHORNOBYL-1, BUT MAY RESTART UNIT 1 OR 2
Ukraine shut down Chornobyl-1 at 10:00 p.m. local time on 30 November 1996. The move fulfilled a vow by Ukrainian President Kuchma, made at the April 1996 Nuclear Safety Summit in Moscow, to take the unit off line by 2000.[1] With Unit 1 shut down, Ukraine loses approximately 4.8 billion kW/hr per year of energy output as well as 1600 jobs in the Slavutych region.[2] Some observers have wondered whether the decision was strictly political, since the safe life of Unit 1 ended in early 1997. At that time, either the management would have taken the reactor off line anyway or replaced and modernized the reactor's channels--an expensive procedure, the funds for which Kiev lacked.[3] In its official application to shut down Unit 1, the ChNPP management cited the need for a comprehensive engineering assessment, especially of the fuel channels, as the reason for the move. According to Chornobyl plant manager Serhiy Parashyn, no document prohibiting the future operation of Chornobyl-1 exists.[2,3] Speculation that the unit may be restarted has arisen due to the plan to keep 1600 fuel assemblies inside Chornobyl-1 for two years. In fact, both Derzhkomatom (the Ukrainian State Committee for Use of Atomic Energy) and Parashyn have reportedly said that Chornobyl-1 will be maintained and, perhaps, restarted if energy is lacking during the winter.[1,4] Nevertheless, Kuchma announced that restarting Unit 1 is not economically viable since it would cost an estimated $225 to $450 million. The high end of this estimate is approximately the same as the estimated cost of completing the Khmelnytskyy-2 or Rivne-4 reactors.[2,5] At an estimated cost of $85 to $280 million, bringing Unit 2 back on line for continued service presents a more likely alternative for immediate power replacement.[2,6,7] Shortly before shutting down Chornobyl-1, Derzhkomatom passed a decree sanctioning such a measure.[2] If allocated by the Ukrainian Government, Unit 2 refurbishment money would probably go towards safety backfits, replacement of isolation valves on the inlets to the fuel channels below the reactor, and borrowing turbines and fuel from Unit 1.[2,8] A recent article, however, expressed some pessimism about restarting Unit 2, placing the earliest possible on-line date in the second quarter of 1998.[7] Thus, only Unit 3 remains in operation at ChNPP.[1]
Sources:
[1] Ann MacLachlan, "Ukraine Shuts Chernobyl-1, Fulfilling Promise To West," Nucleonics Week, 12/5/96, p. 14.
[2] Peter Coryn, "Chernobyl-1 Is Shut But Ukraine Keeps Units 1,2 Restart Option," Nucleonics Week, 1/2/97, p. 14.
[3] Yanina Sokovskaya, "Shutdown of Chernobyl Nuclear Power Station First Unit. Technical Necessity or Political Gesture?," Izvestiya Ukraina, 11/30/96, p. 1; in "Ukraine: 'All the Rules Broken' in Shudown of Chernobyl No. 1 Unit," FBIS-TEN-96-011, 11/30/96.'

[4] NTV, 11/30/96; in "Chernobyl Director Says Shutdown Decision May Not Be Final," FBIS-SOV-96-232, 11/30/96.
[5] UNIAN, 11/29/96; in "Kuchma: No Plans To Restart Chernobyl's Generating Set," FBIS-SOV-96-232, 11/29/96.
[6] Ann MacLachlan, "Chernobyl Managers Want To Reopen Unit 2 To Offset Unit Shutdown," Nucleonics Week, 11/21/96, p.16.
[7] UNIAN, 3/26/97; in "Ukraine: Second Reactor At Chernobyl May Not Be Reconnected," FBIS-SOV-97-085, 3/26/97.
[8] "Chernobyl-1 shut down, Unit 2 may restart in 1997," Nuclear News, 1/97, pp. 33-34.{Revised 7/1/97 MK}{Cleared 7/15/97 JL}

 
9/18/96: CHORNOBYL-1 TO BE PERMANENTLY SHUT DOWN ON 11/30/96
According to Deputy Director General of the Chornobyl NPP Vasyl Omelchenko, the Ukrainian government made its final decision to permanently shut down Unit 1 at Chornobyl on 30 November 1996, which is several months before the reactor's service life expires. Omelchenko said that the decision was made not only because of the agreement signed by the G-7 and Ukraine in Ottawa, but also because nuclear fuel deliveries have been interrupted by the Russian nuclear production company TVEL due to Ukraine's $25 million unpaid bill for the supplied fuel. Chornobyl is completely dependent on TVEL's fuel, which is produced specifically for RBMK-type reactors. However, Omelchenko mentioned that the management of the Chornobyl NPP will soon find financial resources to purchase nuclear fuel from Russia.
[Zakhar Butyrskiy, "Tretiy reactor ChAES skoro budet ostanovlen," Segodnya, 9/18/96, p. 9.]
 
7/1/96: CHORNOBYL HAS NUCLEAR FUEL FOR ONE MONTH ONLY
Ukrainian customers owe $50 million to Chornobyl NPP for energy. According to the chief engineer of the Chornobyl NPP, Vitaliy Tovstonogov, the plant lacks the financial resources to buy nuclear fuel from Russia, because many of the Chornobyl NPP customers are failing to pay their electricity bills. Tovstonogov said that if Chornobyl NPP had to operate at full capacity and the arrival of nuclear fuel from Russia in late June 1996 never took place, the plant would fully consume available nuclear fuel in one or one and a half months.
[Zahar Butyrskiy, "Ukrainskiye AES budut prodavat energiyu so skidkoy," Segodnya, 7/1/96.]{Entered 8/23/96 GN}
 
6/28/96: UNIT 1 AND 3 OPERATION DEPENDS ON ARRIVAL OF RUSSIAN NUCLEAR FUEL
Unit 3 at Chornobyl resumed operating at full capacity, after the arrival of nuclear fuel from Russia on 24 June 1996 under the agreement on supplying Ukraine with nuclear fuel in exchange for the nuclear warheads withdrawn from Ukrainian territory. This first consignment of reactor fuel will last until October 1996, taking into account planned stoppages of the Chornobyl reactors for repairs and maintenance. It is expected that Russia will provide two more deliveries of nuclear fuel, each 50 percent larger than the first, by the end of 1996. Before the arrival of Russian fuel, Units 1 and 3 had been operating at reduced capacity; 50 percent and 40 percent respectively. Unit 1 is temporarily shut down for planned maintenance, with its restart planned for 8 July 1996.
Sources:
[1] UNIAN, 6/28/96; in "Transfer Of Russian Nuclear Fuel Supplies Begins," FBIS-SOV-96-127, 6/28/96.
[2] Jack Ashton, "Chernobyl-1 Faces Crucial Test Phase," NucNet, 6/27/96.
[3] "Russia ships new fuel to Chernobyl plant," Nuclear News, 8/96, p. 72.

 
6/22/96: TEMPORARY SHUTDOWN OF UNIT 1 AT CHORNOBYL
Chornobyl's Unit 1 was temporarily shut down until 6 July '96 for planned short-term repair and maintenance. According to experts from the Ukrainian State Committee on Use of Nuclear Energy, one of the main reasons for the unit's shutdown was the lack of nuclear fuel expected from Russia. During the maintenance work on Unit 1, the power plant's specialists will check on the condition of the unit's zirconium pipes, and report back to a group of state experts by 30 June '96. Based on the findings of the report, experts from the Ukrainian Ministry of Environmental Protection and Nuclear Safety will make a final decision concerning the date of the Unit 1 shutdown.
["1 energoblok Chernobylskoy AES ostanovlen na planovyy remont," Interfax, 24/6/96.]
 
5/23/96: RUSSIAN-UKRAINIAN-U.S. NUCLEAR FUEL SUPPLY AGREEMENT AMENDED
In Kiev, Russian Prime Minister Viktor Chernomyrdin and Ukrainian Prime Minister Yevhen Marchuk amended the Trilateral Statement between the Ukrainian, Russian, and U.S. presidents of 14 January '94, which provided for the delivery of Russian nuclear fuel (1,800 fuel rods) to Ukrainian nuclear power plants, particularly to Chornobyl, from 1994 to 1997. According to the amendment, instead of 155 VVER fuel rods scheduled for delivery in 1996, Russia would deliver 1,040 RBMK fuel rods by the end of 1996.
Sources:
[1] Lesya Mishchenko, "Both Stars And Fate--In The Name Of Ukraine," Demokratychna Ukrayina, 6/22/96, pp. 1-2; in "Udovenko Interviewed On NATO, Bosnia, Russian Election," FBIS-SOV-96-126, 6/22/96.
[2] Alex Brall, "Chernobyl-1 Threatened With Lack Of Fuel, November Closure," Nucleonic Week, 6/13/96, pp. 15-16.

 
4/3/96: DELIVERY OF RUSSIAN FUEL AVERTS UNIT 3 SHUTDOWN
Russia delivered 160 fresh fuel assemblies to Chornobyl-3, alleviating the fuel shortage and averting a shutdown. Unit 3 was operating at nominal power and was expected to be shutdown by the end of March 1996 due to a lack of $2.5 million worth of fuel assemblies from Russia.
Sources:
[1] "Nesmotrya na zadolzhennost Chernobylskoy AES za postavlyaemoe toplivo, Rossiya prodolzhayet ego otgruzku," Rossiyskaya Gazeta, 4/3/96, p. 1.
[2] "Ukraine," NucNet, 4/3/96.

 
2/12/96: CHORNOBYL NPP OPERATES AT 70% CAPACITY
After Ukraine was cut off from the Russian-Ukrainian power grid, capacity utilization at Chornobyl NPP was increased to 100% at Unit 1 and to 80% at Unit 3. The Chornobyl NPP normally operates at around 70% capacity utilization, which is in-line with government standards.
["Nuclear Power Plants Pushed To Compensate For Cut From Power Grids," Post-Soviet Nuclear & Defense Monitor, 3/12/96, p. 7.]
 
1/25/96: UKRAINIAN NPPS NEED $100 MILLION WORTH OF FUEL TO STAY ON-LINE
Ukrainian State Committe for the Use of Atomic Energy (Derzhkomatom) warned that the Ukrainian NPPs need $100 million worth of fuel from Russia to stay on-line. However, because the government is only receiving payment for 13% of the energy produced at the NPPs, Derzhkomatom cannot afford to buy fuel from Russia and may have to cancel production in February or March 1996.
["U Ukrainskikh AES ne khvatayet sredstv na zakupku topliva," Izvestiya-Finansoviye Izvestiya, 1/25/96, p.1.]
 
1995: REPORTS CONFLICT ON CHORNOBYL'S SHARE OF UKRAINE'S ELECTRIC ENERGY
According to the Verkhovna Rada press service, the Chornobyl NPP supplied 6% of Ukraine's total electric energy at the end of 1995 while the plant's capacity utilization was only 50%. This conflicts with other reports citing Chornobyl NPP as having the highest capacity utilization in Ukraine.[1] According to UNIAN, generating capacity through October '95 was more fully utilized at Chornobyl than any other Ukrainian NPP, 69.2% in comparison with an average of 61.1% for Ukraine's nuclear power industry as a whole.[2] For the first ten months of 1995, Chornobyl reportedly produced 16.1% (9085m kilowatt-hours) of the total output for the nuclear industry.[2]
Sources:
[1] "Zabezpechyty natsionalni interesy Ukrainy," Holos Ukrainy, 1/6/96, p. 4.
[2] UNIAN, 11/4/95; in "Ukraine: Chornobyl Nuclear Power Plant Best in Ukraine, Performance Shows," BBC Monitoring Service, 11/17/95.
 
11/6/95: UNIT 1 BROUGHT BACK ON LINE
Unit 1 was brought back on line. It had been shutdown since 27 October 1995.
[IAEA Daily Press Review, 11/6/95, No. 285.]
 
10/23/95: RESTART POSTPONED
Ukraine postponed the restart of Unit 1.
[BBC Monitoring Service, 10/23/95 in "Chornobyl," IAEA Daily Press Review, 10/23/95, p. 2.]
 
10/17/95: UNIT 1 BROUGHT ON LINE AND RECONNECTED TO THE GRID
Unit 1 was brought on line and reconnected to the grid after 39 of the unit's 1692 fuel channels were replaced. Plant management reportedly is considering major fuel channel reconstruction at the three viable Chornobyl units. Fuel channel replacement would allow the units to operate until 2010-2015.
[Peter Coryn, "Chernobyl Runs 'Dress Rehearsal' For Operating Plant After 2000," Nucleonics Week, pp. 5-6.]
 
10/11/95: NUCLEAR REACTORS MAY PROVIDE 40% OF UKRAINE'S ENERGY IN 1996
On this date, only Chornobyl-3 is connected to Ukraine's electricity grid. The remaining reactor is undergoing routine maintenance and reportedly should be reconnected to the grid the week of 16 October '95. Prime Minister Yevhen Marchuk expressed hope that nuclear reactors would provide 40% of Ukraine's energy in 1996.
["Ukraine, G-7 In Talks To Close Chernobyl," Reuter, 10/11/95.]
 
10/1/95: CHORNOBYL NUCLEAR POWER PRODUCTION IN SEPTEMBER
In 9/95, Chornobyl nuclear power plant produced 708.1 kWt/hrs of electricity, which fulfilled 104.9 percent of its plan. The NPP released 647.4 million kWt/hrs into the power system, 106.7 percent of the monthly plan. Reportedly, only Unit 3 was operating in September. During September '95, radiation emissions from the sarcophagus remained within the established norms.
["Chornobyl," UNIAN, 10/3/95 in FBIS-SOV, 10/3/95.]
 
8/95: ONE MORE STEP TO EXTEND CHORNOBYL'S OPERATION
Planned replacement of 13 of the 1600 zirconium fuel channels began in the beginning of August '95. This may be a step in the movement to extend Chornobyl's operation an additional 10 years if the $4.4 billion is not supplied by the West.
["Chernobyl-1 Fuel Channel Replacement Begun In August," Nuclear News, 10/95, p. 46.]
 
8/28/95: REDUCED CAPACITY AT CHORNOBYL'S UNIT 1
Unit 1 operated at only 70-80% of its capacity for safety reasons.
["Interview With Serhiy Parashyn, Director Of The Chornobyl Nuclear Power Plant," Intelnews, 8/28/9.]
 
8/13/95: DERZHKOMATOM IS PLANNING TO EXTEND LIFE OF THREE REACTORS
According to Mykhailo Umanets, Chairman of the State Committee for the Use of Atomic Energy, Ukraine will extend the life of the three undamaged reactors if it does not receive billions of dollars in Western aid. A Derzhkomatom plan to extend the life of the three reactors by ten years requires no foreign aid as the station will sell electric power at US$.03 per kWh. To justify the continued operation of the plant, Umanets cited a number of figures: the Chornobyl NPP fulfilled 104% of its planned quota for the first half of 1995, producing KBV79.4 trillion worth of power, but only received 57% of its payments. During this same period, breaks and errors were reduced by 31%. Unit 1 operated without errors.
Sources:
[1] Serhiy Sokolovskiy, "Nuclear Chief On Chornobyl Reactors," Intelnews, 8/13/95.
[2] "Continued Operation Of Chornobyl NPP Recommended," UNIAN, 7/28/95.

 
8/8/95: NUCLEAR ENERGY COMMITTEE SUPPORTS NON-NUCLEAR POWER PLANTS
The State Committee on the Use of Atomic Energy (Derzhkomatom) reportedly supports the proposal for steam-gas electric plants in Slavutych. The Ministry of Energy supports the modernization of existing coal and gas-oil power plants, which currently make up 67.6 percent of Ukraine's electrical energy capacity.
[Yuriy Orobets, Hennadiy Schastliviy, and Oleksandr Dupak, "What Will We Have Instead Of Chornobyl?" Holos Ukrainy, 9/5/95, p. 6.]
 
8/7/95: CHORNOBYL PRODUCES PROFIT
Chornobyl NPP reportedly produced a profit last year. At local festivities, the plant raffled off over half a million kilowatts of electric power to Ukrainian citizens.
["In Ukraine," Post-Soviet Nuclear & Defense Monitor, 8/7/95, p. 16.]
 
6/15/95: NEW GAS-FIRED PLANT AT CHORNOBYL: PROS AND CONS
There were mixed reactions to the announcement that a new gas-fired plant was to be constructed at Chornobyl as a means to replace the electricity generated by the nuclear units that are slated for closure. Proponents of the idea state that it will increase Western investment and pave the way for future Western-Ukrainian partnerships; additionally the gas-fired plants are very efficient. One of the drawbacks is that gas fuel is more expensive and Ukraine is already deeply in debt to Russia for previous gas deliveries. Minenergo is against the proposal because nearly 40% of Ukraine's generating capacity is sitting idle for lack of fuel; Minister of Energy Vilen Semenyuk has stated that there is no reason then to build new generating units. Mykhailo Pavlovskyi, Chairman of the Rada Standing Commission for Nuclear Policies and Nuclear Safety, and Nuclear Development Subcommittee Chairman Mykola Dudchenko have stated that no final decisions will be taken until a complete feasibility study is finished.
[Peter Coryn and Ann MacLachan, "Ukrainians Have Mixed Reactions To Chernobyl Gas Proposal," Nucleonics Week, 6/15/95, pp. 10-22.]
 
6/12/95: THERMAL GAS POWER PLANT : SUPPORTERS AND OPPONENTS
Supporters of the plan to build a thermal gas power plant to replace Chornobyl's generating capacity include Serhiy Parashin, Chornobyl's plant manager; Mykhailo Umanets, head of Derzhkomatom; and Yuriy Kostenko, Minister of Environmental Protection and Nuclear Safety (MEPNS). The Ministries of the Economy and Energy, as well as the Nuclear Regulatory Administration, within MEPNS argue that ensuring gas supplies is both difficult and expensive. Umanets and Kostenko oppose the setting of a definite timetable for Chornobyl's closure. First Deputy Minister Smyshlyayev, who works for Kostenko, and Kostenko have been at odds over this and reportedly took their debate to Prime Minister Marchuk for mediation.
["Ukrainian Government Negotiating Chernobyl's Future With A Divided Team," Post-Soviet Nuclear & Defense Monitor, 6/12/95, p. 11.]
 
5/27/95: ABB WILL REPLACE CHORNOBYL POWER PLANT WITH ALTERNATIVE ENERGY SOURCES
A Western consortium headed by ABB Asea Brown Boveri Ltd. will work to replace the Chornobyl power plant with alternative energy sources and provide employment for the plant workers. Ukraine signed an agreement with ABB for the conversion of the station into a non-nuclear source. President and CEO of ABB, Percy Barnevik, stated that a gas-fired plant, the most fuel efficient and environmentally safe alternative, should be completely operational in three years; the first installation, 100 kilometers from Chornobyl, should be generating electricity within 24 months. Twelve months later, according to ABB representatives, the plant would be at full capacity--3000 megawatts. ABB has converted nuclear power plants into fossil-fuel burning ones in the United States previously. Estimates of the cost of closing Chornobyl and associated costs range from $1.4-$1.7 billion. Building a new power plant will cost $2.3 billion and the entire project will cost an estimated $10 billion. The consortium, in addition to replacing the nuclear power plant's power capacities, hopes to maintain Chornobyl's social infrastructure, maintain the trained personnel and scientific potential of the Ukrainian nuclear industry, and carry out international financing of the project. The international consortium includes: ABB Kraftwerke AG and Mannesmann (Germany), Stromberg (Finland), Skansa and Vattenfall (Sweden), Danish Power Consult (Denmark), Sulzer (Switzerland), SAE Sadelmi (Italy), ABB Combustion Engineering and CMS Energy Corp. (United States), and Kawasaki Heavy Industries and JGT (Japan). The Ukrainian partners of this consortium include: the State Committee for the Utilization of Atomic Energy (sic), the Ministry of Environmental Protection and Nuclear Safety, the Ministry of Foreign Economic Relations, the National Academy of Sciences, the Chornobyl Nuclear Power Plant, Turboatom, Monolit, Khartron, Dniproenergobudprom, NVP Rotor, AT Budmachin, Energoproyekt Kiev, and Energoproyekt Kharkiv. Siemens AG recently stated that building a gas-fired plant was not the best option for Ukraine given its already substantial debt to Russia for natural gas. The director of Siemens AG predicted that the gas plant would cost $3 billion, plus $300 million per year for fuel imports. Mykhailo Umanets, Chairman of the State Committee for the Use of Atomic Energy, meanwhile stated that the Chornobyl problem will not be resolved until 2025, at the earliest.
Sources:
[1] "Ukraina," Yadernyy Kontrol, 7/95, p. 8.
[2] Intelenws, 5/27/95; in "Accord On Chornobyl Conversion To Non-Nuclear Status Signed," JPRS-TEN-95-008, 5/27/95.
[3] "ChAES budet zakryta, esli na eto naidutsia sredstva," Segodnya, 5/30/95, p. 4.
[4] Ann MacLachan, "ABB Consortium Seeks Western Funds To Replace Chornobyl With Gas," Nucleonics Week, 6/1/95, pp. 6-7.
[5] Serhiy Sokolovskiy, "Special To INTELNEWS," Intelnews, 5/27/95.

 
2/17/95: NEW FOSSIL-FUEL BURNING PLANT WILL BE BUILT IN CHERKASSY OBLAST
The joint-stock company ENERGY that is planning to construct a new fossil-fuel burning plant in the town of Chyhyryn in the Cherkasy Oblast has declared that its main reason for building this new plant is the closure of Chornobyl. ENERGY seeks to create conditions that would facilitate the permanent closure of Chornobyl. This industrial financial conglomerate is the first of its kind to exist in Ukraine; it has 30 member firms and institutions, including "the municipal state energy board, Kyivenergo; Donenergo, a similar board in Donetsk; UkrElectroProject, an educational research institution; and DniproStroyProm, the largest state construction association within the Ministry of Energy." This organization was established by presidential decree on 27 January 95. The president of ENERGY Ravil Abubekerov said that the only realistic method to resolve the Chornobyl closure crisis is to come up with capital to cover the costs of the construction of three 700 MWe fossil fuel plants to replace the electricity generated by Chornobyl. This project will cost an estimated $1.3 billion. ENERGY is seeking Western partners for the project since efficient and environmentally safe technology is not available domestically. One problem with the project may be the choice of location; Chyhyryn is an environmentally protected site and plans to construct a nuclear plant there during Soviet times were halted. The infrastructure of the incomplete nuclear power station at this site is valued at $120 million. Seventy percent of ENERGY's statue fund consists of Ukrainian capital. SIEMENS and IBB have expressed interest in the project.
Sources:
[1] Intelnews (Kiev), 2/17/95; in "Firm Plans To Build Fossil Fuel Plant," FBIS-SOV-95-034, 2/17/95.
[2] "Global Group Formed To Close Chornobyl," InfoBank, 2/20/95.

 
1994: CHORNOBYL CONTINUES TO HOLD SHARE OF ELECTRICITY SUPPLY
In 1994, electricity produced at Chornobyl accounted for 7% of the total supply in Ukraine.
["Nuclear Energy Safety Challenges In The Former Soviet Union: Panel Report," Center for Strategic and International Studies, Washington, 1995, pp. 35-50.]
 
12/22/94: WILL UKRAINE WITHDRAW VERKHOVNA RADA MORATORIUM?
Nur Nihmatullin, first Deputy Chairman of Derzhkomatom, reported that Ukraine was offered a $400 million ECU credit to bring on-line (unspecified) units which had had their construction halted due to a Verkhovna Rada moratorium. According to this politician, Spain also planned on contributing $500 million for a 500 MWt reactor for Ukraine.
[Valentin Smaga, "Nuzhno li Vozrozhdat ChAES?" Kyivskyye Vedomosti, 12/22/94.]
 
12/9/94: UNIT 1 RESTARTED
Unit 1 was restarted. Returning the unit to operation was delayed due to some problems that had been identified during the shut-down inspection. Only one of the unit's turbogenerators is operational; the other is still undergoing repairs.
["Unit One At Chernobyl Back On-line," Nucnet, No. 588-589, 12/9/94.]
 
10/10/94: SHORTAGE OF FUNDS MEANS NO FUEL RESERVES AT CHORNOBYL
As a result of Ukraine's shortage of funds with which to buy nuclear fuel from Russia, the two units at Chornobyl were forced to refuel directly from the fuel transport car that delivered the assemblies; there were no reserves of fuel left at the plant. Ten fuel reloads were required for the first six months of 1994, but only two were actually delivered. The Trilateral Statement of 14 January '94 stipulated that Ukraine receive 430 fuel assemblies; thus far, only 180 have been received. The 250 additional assemblies should be delivered by the end of the year, but Ukraine needs 550 fuel assemblies for the VVERs and 800 for the RBMKs.
["Financial Crunch Puts Ukraine On Verge Of Running Out Of Fuel," Nuclear Fuel, 10/10/94, pp. 18-19.]
 
2/23/94: KUCHMA'S DIRECTIVE ON DEVELOPING OF NUCLEAR POWER
Ukrainian President Leonid Kuchma signed a directive, "On Urgent Steps to Develop Nuclear Power and Complete the Nuclear Fuel Cycle in Ukraine." The directive provides for the introduction of four new nuclear reactors, the restart of Chornobyl's Unit 2, and the completion of the nuclear fuel cycle in Ukraine.
[UNIAN (Kiev), 4/5/94; in "Ministries Demand Cancellation of Nuclear Directive," FBIS-SOV-94-067, 4/7/94, p. 51.]
 
10/21/93: CHORNOBYL TO BE KEPT OPEN; MORATORIUM TO END
The Ukrainian Parliament voted (221-38) to keep the Chornobyl nuclear power plants open past the end of 1993 and to end the moratorium on the construction of new nuclear power stations in the country. This decision was taken in light of the power shortage in Ukraine; nuclear power currently generates nearly one-third of Ukraine's energy. Given the difficulties Ukraine is having in making its payments to Russia for energy supplies, Ukraine's indigenous energy supplies will become increasingly important. Units 1 and 3 will continue operation. Unit 2, closed after a serious fire in October '91, may be restarted. The Parliament's action reversed a 1991 decision to close the entire power station on 3 December '93 Mykhailo Umanets, Chairman of the State Committee for the Use of Nuclear Power, said the decision would secure increased capacity of 18,000 megawatts within the next year. Ukrainian deputies stated that this reversal of policy was possible due to a dramatic change in both society's and government's attitudes. Evidence of society's change came out in a study of media reports that found 49 percent of all statements published in the first half of 1993 about nuclear power "had a positive coloring," in contrast to the five years following the Chornobyl disaster when only 4 percent of the reports were positive Chairman of the UkrSCNRS Nikolai Steinberg expressed the government's current opinion, commenting that "the current level of operational safety at Chornobyl allows me to conclude that operation without major risks is possible."
Sources:
[1] "Chernobyl To Continue Operating, "Surviving Together, Winter 1993, p. 51.
[2] Ann MacLachlan, "Ukrainian Regulator Resigns To Protest Chernobyl Decision," Nucleonics Week, Vol. 34, No. 49, 12/9/93, pp. 11-12.
[3] Ron Popeski, "Ukraine Votes To Keep Chernobyl Open," Reuter, 10/21/94.
[4] ENS NucNet, 12/10/93.
[5] Le Point (Brussels), 11/6/93, p. 51; in JPRS-TEN-93-027, 12/15/93, pp. 56-57.

 
9/93: KALNYUK REPORTS ON UNIT 2 RESTART
V. Kalnyuk, first deputy to the presidential representative in the Lviv Oblast, reported that Unit 2 would be restarted. This decision was made at the 9 September Cabinet of Ministers meeting. The power supplied by Unit 2 should save an estimated 3.3 million tons of coal in Ukraine.
[Post Postup (Lviv), 9/13/93; in "Energy Outlook Detailed; 3d Chornobyl Block To Open," FBIS-SOV-93-177, 9/15/93, p. 57.]
 
5/6/93: CHORNOBYL REACTORS WERE USED TO PRODUCE IRRADIATED SILICON
It was recently revealed that the Chornobyl reactors have been used for much of the decade to produce irradiated silicon, which is a material with semiconductor properties. The silicon may have been produced for the Soviet defense sector as well as for export abroad to Eastern Europe in exchange for hard currency.
[VESTI Television Program (in Russian), 5/6/93.]
 

Page last updated July 1997
This file is no longer being updated.  For information on developments in the nuclear power industry, please see the Ukraine: General Nuclear Power Developments section.

Comments or questions? Contact Michael Jasinski at MIIS CNS: Michael.Jasinski@miis.edu

CNSThis material is produced independently for NTI by the Center for Nonproliferation Studies at the Monterey Institute of International Studies and does not necessarily reflect the opinions of and has not been independently verified by NTI or its directors, officers, employees, agents. Copyright © 2002 by MIIS.

HOME  |  CONTACT US  |  SITE MAP