Features

This material is produced by the Monterey Institute's Center for Nonproliferation Studies
What's New Ukraine Research, Power & Waste Power Reactors Khmelnytskyy
Khmelnytskyy Summary
Developments
Spent Fuel and Radioactive Waste
Reactor Incidents Table


Ukraine: Developments at Khmelnytskyy
This is an archived page. Please visit the new Ukraine country profile

Ukraine: Khmelnytskyy NPP Developments

This file is no longer being updated.  For information on developments in the nuclear power industry, please see the Ukraine: General Nuclear Power Developments section.

(To see the criteria Profiles uses to select materials for inclusion in the Power Reactors files, click here.)

3/20/2001: ENERHOATOM PLANS CONSTRUCTION OF KHMELNYTSKYY NPP UNITS 3 AND 4 BY 2010-2014
Enerhoatom Executive Director of Production Viktor Stovbun stated on 20 March 2001 that current plans anticipate completion of Khmelnytskyy NPP Units 3 and 4 by 2010-2014.  According to Stovbun, decisions regarding the further construction of Units 3 and 4 will be made after the completion of Khmelnytskyy Unit 2 and Rivne Unit 4.[1]  On 29 January 2001, Khmelnytskyy NPP Director Volodymyr Sofiyuk had said that construction work on Units 3 and 4 had been halted indefinitely, as the reactor type had not yet been chosen and there were no specific plans for completion.[2]  Henadiy Sazonov, Enerhoatom project director, said in December 2000 that Russian VVER-1000 reactors would not be chosen for Units 3 and 4, and the model would be determined through an international tender.[3]  However, Stovbun's remarks on 20 March 2001 suggested that Russian VVER-1000 reactors or their more modern variants might be chosen, because construction work already completed on the units is suited for a Russian reactor type.[1]
Sources:
[1] "Tretiy i chetvertyy energobloki Khmelnitskoy AES mogut byt dostroyeny v 2010-2014 gg.," Interfax, 20 March 2001. 
[2] "Ukraina ne vedet dostroyku blokov Khmelnitskoy AES - direktor stantsii," Interfax, 29 January 2001. 
[3] "No VVERs for Khmelnitsky 3 and 4," Nuclear Engineering International, December 2000. {Entered 5/25/01 RG}
 
1/15/2001: ENERHOATOM AND KUCHMA EMPHASIZE NECESSITY OF COMPLETING NEW  POWER UNITS AT KHMELNYTSKYY AND RIVNE NPPS
On 15 January 2001, Enerhoatom announced that completion of the power units under construction at the Khmelnytskyy and Rivne NPPs is necessary due to the limited supply of fossil fuel for regional electrical power plants and the high cost of importing fuel.  Enerhoatom said that the regional power plants are obsolete and past the end of their service lives, and the decision to complete the power units is both economically and environmentally justified.[1]  Ukrainian President Kuchma similarly emphasized the need to complete the Khmelnytskyy and Rivne NPP power units during a meeting with Chornobyl NPP leadership on 20 February 2001.  Kuchma said that Ukraine must complete the power units even if the EBRD fails to provide the funding that was promised by a Memorandum signed with the G-7 in 1995.  His statement came after the EBRD informed Ukrainian officials that the bank directors were reconsidering renewal of their funding program to Ukraine.  Kuchma expressed his dissatisfaction with international finance organizations, saying that they have continually attached new conditions to their aid to Ukraine and show a lack of desire to fund the construction of the power units.[2]
Sources: 
[1] "Dostroyka blokov ukrainskikh AES - yedinstvennoye ekonomicheski i ekologicheski opravdannoye resheniye, schitayut v 'Energoatome'," Interfax, 15 January 2001. 
[2] "Prezident Ukrainy vyskazyvayetsya za dostroyku Khmelnitskoy i Rovenskoy AES," Interfax, 20 February 2001. {Entered 5/30/01 RG}
 
8/20/2000:  UKRAINE PLANS TO FINISH BUILDING ADDITIONAL NPP POWER UNITS WITHOUT WESTERN AID
As reported by Interfax on 20 August 2000, Ukrainian Deputy Prime Minister Yuliya Tymoshenko announced that Ukraine can independently finish building Unit 2 of the Khmelnytskyy NPP and Unit 4 of the Rivne NPP due to increases in energy revenues.[1,2]  The estimated $700-800 million cost of constructing the two new units will be financed by increased electricity tariffs, collecting energy debts owed to Enerhoatom by construction firms and equipment suppliers, as well as Russian credits in the form of equipment and the first nuclear fuel load for the reactor.  ITAR-TASS reported that Enerhoatom intends to use Russian and Ukrainian equipment to complete the construction of the power units. However, automated control systems for the reactors may be purchased from Western firms.[3]  The additional Rivne and Khmelnytsky units would compensate for the final shut-down of the Chornobyl NPP.[4] 
Sources:
[1] "Ukraina sposobna samostoyatelno dostroit atomnyye energobloki- vitse-premier," Interfax, No.1, 20 Aug 2000.
[2] "Ukrainian Energy Market to Finance Construction of Nuclear Power Plant Units," Interfax, No. 3, 20 July 2000.

[3]  ITAR-TASS, 21 Aug 2000; in "Ukraine:  Nuclear Plants to Use Domestic, Foreign Components," FBIS Document CEP20000821000189.
[4]  Interfax, 6 June 2000; in "Russia:  Deputy Minister Regrets Decision to Close Chernobyl," FBIS Document CEP20000606000139.{Entered 9/14/2000  RG}


5/16/2000: UKRAINE MAY  HOLD NEW TENDER FOR RIVNE AND KHMELNYTSKYY NPP CONSTRUCTION PROJECTS
Yulia Tymoshenko, Deputy Prime Minister of Ukraine, told Interfax on 16 May 2000 that the government may hold a new tender for the Rivne and Khmelnytskyy NPP construction projects if the present contractor [not named in report] does not lower its price.  The original tender was for the amount of  $1.4 billion, however the contractor then presented a figure of $2 billion to complete the work. Tymoshenko said that if the contractor does not lower its price to the original figure, Ukraine can legally hold a new tender for the contract.
["Ukraine may call new tender to complete nuclear reactors," Interfax, 16 May 2000, Vol. V, Issue 89; in FBIS Document CEP20000516000182.] {Entered 5/17/2000 GD}
 
3/25/2000:  ATTEMPT MADE TO STEAL NUCLEAR FUEL AT KHMELNYTSKYY NPP
The UT-1 television news presented a story on 25 March 2000 concerning the uncovering of "a group of dealers" attempting to steal nuclear fuel from the Khmelnytskyy NPP and smuggle it out of the country.  Members of the group have been arrested.  UT-1 reported that the fuel was to be sold for $500,000 per container in Moldova.  No details were given about the group.  UT-1 also reported that six criminal charges had been filed against several Khmelnytskyy NPP managers for illegal barter operations resulting in the theft of 800,000 hryvnyas (about $146,000 as of 25 March 2000).  According to the report, law enforcement agencies now control all transactions at the plant. (Other reports of attempted theft of nuclear materials from nuclear power plants may be found in the NIS Nuclear Trafficking Database.)
[UT-1 Television, 25 March 2000; in "Ukraine: Fuel Theft at Nuclear Plant Thwarted," FBIS Document CEP20000326000081.] {Entered 3/31/2000 GD}
 
2/7/2000: KHMELNYTSKYY-2 CONSTRUCTION MATERIALS STOLEN, SALE THWARTED
On 7 February 2000, Volodymyr Vezdenetskyy, deputy head of the investigative directorate of the Khmelnytskyy Oblast branch of the Internal Affairs Ministry, told journalists that his directorate was investigating the theft of six 495kg pipe covers, used in the reactor's emergency cooling system.  The perpetrators were discovered when they tried to sell two of the covers, which cost more than 52,000 hryvnyas apiece (over $9000 as of 8 February 2000), to a scrap metal dealer for 1600 hryvnyas (about $283 as of 8 February 2000).  Vezdenetskyy said that the thieves were probably foremen involved in the construction of Unit 2.  Due to the weight of the items in question, a crane operator and a truck driver were also necessary.
[Mikhail Vasilevskiy, "Neveroyatnaya krazha na Khmelnitskoy AES," Den online edition, http://www.day.kiev.ua, 8 February 2000.]{Entered 3/30/2000 CC}
 
1/12/2000:  TWO FORMER KHMELNYTSKYY NPP MANAGERS SOUGHT FOR CRIMINAL WRONGDOING
Ukrainian authorities are searching for former Khmelnytskyy NPP director Viktor Sapronov and a former deputy director, Mr. Teplov. Sapronov is sought in connection with transferring almost $20,000 in plant funds to his dentist. In addition,  Sapronov is accused of transferring almost 1 million hyrvnyas (about $181,000 as of 12 January 2000) to a pension fund.  Sapronov disappeared after learning of the charges against him.[1,2] Deputy Director Teplov is being sought on charges that he was involved in suspicious transactions between the NPP and commercial structures.[2]
Sources:
[1] "Uslugi stomatologa oboshlis direktoru AES v $20 tysyach," Segodnya online edition,  http://today.viaduk.net,14 December 1999.
[2] Andriy Sek, "Draconian methods in the year of the dragon? How shall we fight corruption and organized crime," Ukrayina Moloda, 12 January 2000; in "Scale of Ukraine Corruption, Tasks Seen," FBIS Document FTS20000125000958. {Entered 3/23/2000 GD}
 
9/29/99: EBRD DEFERS DECISION ON FINANCING KHMELNYTSKYY-2 AND RIVNE-4
As Ukraine moves to complete Khmelnytskyy's Unit 2 and Rivne's Unit 4, which are scheduled to be put into operation after the closure of the Chornobyl NPP, prospects of receiving Western loans for the project are uncertain.[1,2] In 1995, the G-7 countries promised to allocate $800-900 million to complete the two reactors.[1,3] The European Bank for Reconstruction and Development (EBRD) tentatively agreed in early 1999 to advance a $190 million loan for the reactors' completion.[4] However, the EBRD is postponing its final decision, insisting that prior to receiving the loan, Ukraine must meet international nuclear safety requirements, reduce barter payments for electricity,[5] privatize regional energy firms,[5,6] indicate a date for shutting down the Chornobyl NPP, and separate assets belonging to the Chornobyl NPP from Enerhoatom.[7] The EBRD's decision is further contingent upon the positions of the individual European governments that would grant the loan. While Germany, for example, has refused to allocate any funds until it carefully reviews the results of the German-Ukrainian negotiations,[8,9] France and Finland have been supportive of assistance.[10,11] The total financial package for completion of the reactors is estimated at $1.75 billion, of which the EBRD would cover 10 percent, the Financial Times wrote on 29 September 1999.[6]
Sources:
[1] "EBRD Chernobyl Proposals Rejected," Nuclear Engineering International, June 1999, p.8.
[2] "Kuchma: G7 Will Stand By Pledge To Finance Nuclear Facilities," Interfax, 29 April 1999.
[3] Igor Kudrik, "EBRD Indecisive, Russia Cautious," Bellona web site, www.bellona.no/e/russia/990215.htm, 15 February 1999.
[4] Tony Wesolowsky, "Ukraine: EBRD Plans To Fund Controversial Nuclear Reactors," Radio Free Europe,www.rferl.org/newsline/1999/02/170299.html, 29 January 1999.
[5] "EBRD Stalls on N Industry Loans," Ukrainian Weekly, 25 April 1999, p. 2.
[6] Financial Times, 29 September 1999, p. 3; in "Condition on Ukraine Loan," Lexis-Nexis Academic Universe, http://web.lexis-nexis.com/universe.
[7] UNIAN, 30 April 1999; in "Talks With European Bank on Future of Chernobyl Plant Continue," Lexis-Nexis Academic Universe, http://web.lexis-nexis.com/universe.
[8] Interfax, 17 June 1999; in "Ukrainian Officials Discuss Debt Issues With IMF Head," FBIS Document FTS19990618000043.
[9] Intelnews,16 July 1999; in "Germany Withholding Financing of Ukrainian," FBIS Document FTS19990716000577.
[10] "Frantsiya podderzhit v YeBRR proyekt dostroyki reaktorov na 2-kh ukrainskykh AES, Interfax, 23 April 1999.
[11] "EU Must Help Ukraine in Building Nuclear Reactors - Finnish PM," Interfax, 23 July 1999. {Entered 10/11/99 SK}
 
9/9/99: RUSSIA WILL ASSIST UKRAINE IN CONSTRUCTION OF KHMELNYTSKYY-6 AND RIVNE-4
Russia has earmarked $60-70 million in its 2000 budget to aid in the completion of Unit 4 of the Rivne NPP and Unit 6 of the Khmenlnytskyy NPP.[1] This aid will come in the form of equipment and nuclear fuel for the two nuclear reactors.[1,2]
Sources:
[1] Intelnews, 9 September 1999; in "Russia to Fund Ukrainian Nuclear Reactor Construction," FBIS Document FTS19990910000130.
[2] "Russia Ready to Fill Ukraine's Nuclear Energy Gap," Jamestown Monitor, 23 July 1999. {Entered 10/7/99 SK}
 
7/9/99: GERMANY PREFERS NON-NUCLEAR ENERGY OPTIONS TO COMPLETION OF KHMELNYTSKYY-2 AND RIVNE-4
Ukrainian President Leonid Kuchma and German Chancellor Gerhard Schroeder met on 9 July 1999 to discuss completion of Khmelnytskyy's Unit 2 and and Rivne's Unit 4.[1] Germany has been trying to persuade the Ukrainian government to consider non-nuclear energy alternatives to compensate for energy losses after the Chornobyl NPP is decommissioned.[2] The German authorities would prefer to provide Ukraine with modern fossil-fuel or gas-fired facilities, rather then funding construction of Khmelnytskyy's Unit 2 and Rivne's Unit 4, which are 80 percent complete.[1,2] The Ukrainian government, nevertheless, insists on finishing the nuclear reactors, pointing out that the non-nuclear option would cost $842 million more than the $1.1 billion needed to complete the construction of the two nuclear reactors.[1] If the Western countries do not provide Ukraine with financial help, Ukraine will finish the construction of the two reactors with Russian help or by itself.[1,3] In this case, the reactors would be completed without any of the safety upgrades envisioned by the EBRD. Nevertheless, it seems likely that the Schroeder cabinet will eventually approve German aid for the reactors, since former German Chancellor Helmut Kohl committed his country to assist Ukraine in constructing the reactors.[1]
Sources:
[1] Mark Hibbs, "Ukraine Rejects German Offer to Replace K2/R4 With Gas, Coal," Nucleonics Week, 15 July 1999, pp.6-7.
[2] Ukrayinske Radio Second Program, 8 April 1999; in "Germany Will Not Fund New Nuclear Plants in Ukraine," FBIS Document FTS19990408001857.
[3]"EBRD Chernobyl Proposals Rejected," Nuclear Engineering International, June 1999, p.8. {Entered 10/14/99 SK}
 
5/11/99: ENVIRONMENTAL GROUPS OPPOSE CONSTRUCTION OF KHMELNYTSKYY-2 AND RIVNE-4
Environmental and anti-nuclear groups oppose construction of Khmelnytskyy's Unit 2 and Rivne's Unit 4, UNIAN reported on 11 May 1999. The Ukrainian environmental organization Zelenyy Svit (Green World) says that the project violates the law on finishing construction of the reactors and safety principles. Zelenyy Svit further pointed out that the reactors did not pass the state environmental assessment examination.[1] European environmental groups also pronounced the project economically and environmentally unsound. They urged the EBRD not to finance the construction and to consider alternative energy sources. According to Charles Frank, EBRD's first vice president, the Khmelnytskyy and Rivne reactors have more advanced designs than the Chornobyl reactor and have been upgraded to Western safety standards.
Sources:
[1] UNIAN, 11 May 1999; in "Environmentalists Oppose Two New Reactors," FBIS Document FTS19990514000752.
[2] Gill Tudor, "EBRD Defends Kiev's Controversial Plans for Nuclear Power Projects," New Europe, 26 April-2 May 1999, p. 22. {Entered 10/14/99 SK}
 
9/19/98: YELTSIN PLEDGES $180 MILLION FOR COMPLETION OF KHMELNYTSKYY-2 AND RIVNE-4
In an informal meeting between Ukrainian and Russian Presidents Leonid Kuchma and Boris Yeltsin in Moscow Oblast on 19 September 1998, Yeltsin promised to allocate $180 million in the 1999 budget for completion of Khmelnytskyy's Unit 2 and Rivne's Unit 4.[1,2] According to President Kuchma, the $180 million will come in the form of technology and fresh nuclear fuel. Kuchma further stated that Ukraine and Russia will cooperate in completing the construction of the two reactors regardless of the final decision of the EBRD on financing the project. According to Yuriy Bespalko, press secretary of Minatom, no concrete figures were named, nor more contracts signed, at the Yeltsin-Kuchma meeting.[3]
Sources:
[1] Interfax, 19 September 1998; in "Yeltsin, Kuchma Agree to Set up Joint 'Anticrisis Group'," Lexis-Nexis Academic Universe, web.lexis-nexis.com/universe.
[2] Viktor Lugovik and Viktor Yadukha, "Rossiya zaplatit za ukrainskiye reaktory," Segodnya, online edition, www.ipres.ru, 13 October 1998.
[3] "Kuchma rasskazyvayet skazki," Anti-atom Press, No. 182, 2 October 1998. {Entered 10/29/99 SK}
 
 6/30/97: KHMELNYTSKYY-1 POWER SUPPLY DISRUPTED
A defect in an auxiliary transformer on a 330 kV transmission cable interrupted power to Unit 1 during the reactor's planned maintenance.  For 90 minutes on 30 June 1997 the reactor was without power, according to the Information Center of the Ministry of Environmental Protection and Nuclear Safety.  Emergency sources of power, including three diesel generators to supply electricity to the reactor's safety control system and accident prevention equipment, came on line during the outage. In less than an hour, workers restored power to Khmelnytskyy-1 by attaching another cable.
[UNIAN, 1 July 1997; in "Ukraine: Fault Disrupts Power Supply to Khmelnitskiy Nuclear Plant," FBIS-SOV-97-182.]{Entered 11/24/97 AjP}
 
5/5/97: KHMELNYTSKYY-1 CLOSED FOR PLANNED MAINTENANCE
Unit 1 at the Khmelnytskyy NPP was shut down on 5 May 1997 for scheduled repairs, according to Derzhkomatom. The 73-day maintenance period will include spent fuel removal, fuel casing examinations, and safety system cooling duct restoration. Radiation levels remained stable during the shutdown.
["Ukrainian Nuclear Station Stops Unit for Routine Maintenance Works," RIA-Novosti Hotline, 5 May 1997.]{Entered 10/24/97 AjP}
 
2/18/97: FRANCE AND UKRAINE TRY TO ATTRACT FUNDING FOR NEW REACTORS
At a press conference on 18 February 1997, Electricite de France (EdF) Director Jean-Pierre Baret stated that twenty French nuclear power engineering experts and Ukraine's Energoatom are working to form a group to develop proposals designed to attract Western investment for the completion of Khmelnytskyy-2 and Rivne-4. EdF serves as a consultant to Derzhkomatom. At the press conference, Derzhkomatom Deputy Chairman Anatoliy Chernov also announced that Ukraine will seek tenders by 2000 for selecting a new type of reactor for NPPs in Ukraine. Chernov noted that France has "a good chance of winning this tender."
[Intelnews, 21 February 1997; in "Ukraine: State Firm, French Experts To Cooperate on Nuclear Units," FBIS-SOV-97-035, 21 February 1997.]{Entered 8/1/97 MK}
 
12/9/96: KHMELNYTSKYY-1 SHUT DOWN DUE TO FALLING PRESSURE
At 7:15 p.m. local time on 9 December 1996, Unit 1 at the Khmelnytskyy NPP underwent emergency closure after pressure fell in the unit's first circuit.  The decrease of  Khmelnytskyy-1 pressure resulted from a power fluctuation in the turbogenerator brought on by a flaw in the turbine regulating system, according to a power plant spokesman.  Power generation is expected to resume on 10 December 1996.  No fluctuations in background radiation at the plant occurred, and the event measured zero on the International Nuclear Event Scale.
[Interfax, 10 December 1996; in "Ukraine: Falling Pressure Forces Closedown of Nuclear Power Unit," FBIS-SOV-96-239.]{Entered 10/24/97 AjP}
 
10/12/96: KHMELNYTSKYY-1 UNDERGOES EMERGENCY SHUTDOWN: INES-0
According to the Ukrainian Ministry of Environmental Protection and Nuclear Safety, Unit 1 at the Khmelnytskyy NPP, which had been operating at full capacity, was shut down due to a fault in an auxiliary pipeline in the reactor. The malfunction resulted in a radioactive water leak, which remained within the containment vessel of the reactor. ITAR-TASS reported that the temporary shutdown resulted from a leak in an air-valve flange on the generator. The leakage did not increase levels of radiation at or around the plant and was given a preliminary rating of zero on the International Scale of Nuclear Events (INES). According to Ukrainian sources, Unit 1 was restarted following necessary repair work on 10/15/96.
[UNIAN, 10/14/96; in BBC Monitoring Service, "Ukraine: Fault Closes Reactor at Khmelnitskiy Nuclear Plant," 10/18/96.] {Entered 12/31/96 GN}
 
7/26/96: TWO NUCLEAR ACCIDENTS KILL WORKER AND LEAK RADIATION: INES 3
Two nuclear accidents at Unit 1, which has been undergoing scheduled large-scale repairs since 7/20/96, killed an employee and released radiation into Unit 1's interior halls. The first accident took place during testing before Unit 1's scheduled restart when a steam pipe burst, killing a worker. The second accident occurred several hours later when radioactive water from the circuit leaked into the nitrogen storage area after plant workers failed to conduct a safety check. According to plant management, radioactive contamination was limited to an inside area and was rapidly eliminated. Both accidents were rated level 3 on the INES seven-point scale for nuclear accidents.
Sources:
[1] Chrystyna Lapychak, "Two Accidents at Ukrainian Nuclear Plant Kill Worker, Release Radiation," Omri Daily Digest, 7/26/96.
[2] Natalya Kondratyuk, Russian Public Television (Moscow), 7/26/96; in " 'Staff' Blamed for Khmelnitskaya Nuclear Accident," FBIS-SOV-96-146, 7/26/96. {Entered 10/25/96 GN}
 
5/30/96: BRITISH GOVERNMENT AID
According to the Minister of Environment and Nuclear Safety Yuriy Kostenko, the British government has provided $80,000 to buy equipment for a training facility (see entry 9/95 below) under construction in Khmelnytskyy.
[EXECUTIVE NEWS SERVICE, 5/30/96, No. 278]
 
4/20/96: EBRD WILL PROVIDE $975 MILLION TO COMPLETE KHMELNYTSKYY AND RIVNE NPPs
The European Bank for Reconstruction and Development (EBRD) reportedly has been influenced by the G-7 to take the lead in raising at least$975 million (650 million pounds) to complete the Khmelnytskyy and Rivne NPPs.
[Mary Brasier, "West Faces Soaring Cost Of Chornobyl," Daily Telegraph, 4/20/96, p. 17.]
 
4/14/96: UKRAINE APPEALS TO EBRD FOR MORE MONEY FOR EXPANSION OF NUCLEAR SECTOR
The EBRD is considering granting $1 billion to Ukraine to complete the Khmelnytskyy and Rivne reactors. Petro Hermanchuk, the Ukrainian Finance Minster, appealed to the EBRD board to lend even more money to Ukraine for this expansion of the nuclear sector.
[Peter Rutland, "Ukraine Pleas For More Cash For Chornobyl," Omri Daily Digest, 4/15/96.]
 
3/96: TRAINING CENTER AND COMPUTER MODELS AT KHMELNYTSKYY
According to the US Department of Energy (DOE), plant analyzers and computer models have been developed for the nuclear power plant simulators at Khmelnytskyy. A training center has also been set up there.
[Working Document to the Scientific and Technological Options Assessment Panel of the European Parliament, "Nuclear Safeguards and Nuclear Safety in the East," November 1996, p. 45.] {Entered 10/17/97 JP} 
 
2/18/96: UNIT 1 WILL COMPENSATE FOR ENERGY LOST AT ZAPORIZHZHYA UNIT 2
Khmelnytskyy Unit 1 was brought on line following completion of repairs. According to the Minister of Energy, Oleksiy Sheberstov, this unit was to compensate for energy lost at Zaporizhzhya Unit 2, which is not working at normal capacity due to a lack of fuel.
["Nuclear Power Plants Pushed To Compensate For Cut From Power Grid," Post Soviet Nuclear and Defense Monitor, 3/12/96, pp. 7-8.]
 
2/15/96:ELECTRICITE DE FRANCE WILL HELP TO COMPLETE KHMELNYTSKYY AND RIVNE
The cost of completing Khmelnytskyy Unit 2 and Rivne Unit 4 has been estimated to be around $1 billion by Electricite de France. Khmelnytskyy Unit 2 was 85.5% completed when construction was stopped. With significant safety upgrades through collaboration with Western firms, the new timeline would have it on line by 2000.
[Ann MacLachlan, "EBRD Studying Request To Fund Completion Of Ukrainian Reactors," Nucleonics Weeks, 2/15/96, pp. 1-2.]
 
2/12/96: EBRD WILL PARTICIPATE IN FINAL STAGES OF KHMELNYTSKYY AND RIVNE CONSTRUCTION
The EBRD reportedly was considering participation in the final stages of construction of Khmelnytskyy Unit 2 and Rivne Unit 4. It planned to give Ukraine financial estimates of these projects before the nuclear safety summit in Moscow in 4/96.
["EBRD Into New Reactors," Eastern Economist, 1/12/96, p. 4.]
 
1/31/96: ANONYMOUS CALL THREATENS TERRORIST ATTACK AT KHMELNYTSKYY NPP
The Khmelnytskyy NPP received an anonymous call warning of an imminent terrorist attack on the plant, according to the Ministry of Environmental Protection and Nuclear Safety.
["Ukraine: Nuclear Power Plant Put On Terrorist Alert," UNIAN, 1/31/96.]
 
1/21/96: SHORT CIRCUIT AT UNIT 1
Unit 1 was shut down due to a short circuit. It was brought back on-line and reconnected to the grid on 2/19/96 following repairs.
[Interfax, 2/19/96; in "Russia: No 1 Unit At Khmelnytskyy Nuclear Plant Back In Operation," BBC Monitoring Service, 2/23/96.]
 
1/11/96: PLANT MANAGERS SAY THAT RADIATION LEAK WAS NO THREAT
A failure in the plant's gas purification system resulted in a radiation leak into the atmosphere. The daily curie rate was 30.5 instead of the normal 5. The plant managers reported that the leak did not pose a threat to people in the area.
["AES Radiation Leak," Eastern Economist, 1/15/96, p. 18.]
 
12/19/95: UNIT 1 INCIDENT - 0 ON INES
Unit 1 was cut off from the network due to hydrogen leaking from a crack in a pipe leading to the cooling unit. The combustion of this hydrogen was stopped 10 minutes after the unit was taken off-line. REUTER reported that the reactor was taken off the electricity grid but was not shut down completely. The reactor was brought back on-line six hours later. This incident was rated a zero on the INES scale. There were no breaches of radiation limits or safety conditions at and around the station.
Sources:
[1] "Znovy Zaymannya Na AES. Tsyoho Razy Vodnyu," Holos Ukrainy, 12/21/95, p. 1.
[2] "Accident At Khmelnytskyy Nuclear Power Station," ITAR-TASS, 12/19/95.
[3] "Small Fire Halts Ukraine Nuclear Power Output," Reuter, 12/20/95.
 
12/95: UNIT 2 WILL BE BROUGHT ON LINE IN TWO AND A HALF YEARS
Unit 2, which is 85% complete, can potentially be brought on line in two and a half years. Electricite de France (EdF) has presented plans for the upgrading and completion of this unit. EdF will work as a consultant as the unit is completed.
["Data Features: World Nuclear Generating Capacity 1993/94," 12/95, p. 45.]
 
10/2/95: UNIT 1 IS BROUGHT BACK ON LINE
Unit 1 was brought back on line. It had been switched off on 9/30/95 due to a leaking component of the hydrogen cooling system.
["Ukraine: Khmelnytskyy Nuclear Power Plant Back To Full Capacity," BBC Monitoring Service; in Reuter Insurance Briefing.]
 
9/95: TRAINING CENTER IS ESTABLISHED AT KHMELNYTSKYY
A training center with a simulator, financed by the United States, is being established at Khmelnytskyy . A contract to supply the simulator was signed with S3 Technologies at the end of 1994. As part of a wider program to improve training and plant safety, Ukraine has a policy (but not a law) to provide simulators for each nuclear sight. Support for computer safety assessment techniques comes from the United States, Germany, France, and Canada.
Sources:
[1] Janet Wood, "The Simulator Explosion," Nuclear Engineering International, 9/95, p. 50.
[2] "Ukraine," by Nikolai Kurilchik and Alexei Breus, Nuclear Europe Worldscan, 7-8/95, p. 77.
 
9/30/95: UNIAN REPORT
According to the UNIAN news agency, Unit 1 was taken off line due to a fault in the power generator. On 9/26/95 a high-voltage line had disconnected and power at Unit 1 dropped to 760 Mw. There was no change in background radiation.
["Ukraine: Emergency Stoppage At Ukraine's Khmelnytskyy Nuclear Power Plant," BBC Monitoring Service, 10/9/95, p. 20.]
 
8/7/95: INCIDENT AT KHMELNYTSKYY UNIT 1 PROMPTS SHUTDOWN
There was an emergency shut-down at Unit 1. According to the information center at the NPP, the shutdown was triggered by a rise in water level and the failure of level sensors in Steam Generator 1. The incident radiation was reported to be unchanged and the established limits of safe operation were not transcended. The turbogenerator of the first reactor was reactivated on 8/8/95. Level sensors in the steam generator reacted to a false signal that the level was lowering, according to the plant's press office. An investigation into what triggered the false alarm is under way.
Sources:
[1] "Otklyuchen Turbogenerator Pervogo Energobloka Khmelnytskoy AES," Segodnya, 8/22/95, p. 1.
[2] "Emergency shutdown of Khmelnytskyy Nuclear Power Station," ITAR-TASS, 8/8/95/.
[3] "In Ukraine", Post Soviet Nuclear and Defense Monitor, 9/1/95, p. 15.
[4] "Nuclear Power Plant Reactivated," Interfax, 8/8/95.
 
7/15/95: LEAKAGE OF OIL FROM TRANSFORMER
A generating set (unspecified) was stopped due to leakage of oil from the set's transformer. The background radiation is within normal levels. An investigation into the causes of the accident is underway.
["Khmelnytskyy Nuclear Plant Stopped Due to Leakage," UNIAN, 7/15/95.]
 
1/16/95: CIRCULATING PUMPS WERE DISCONNECTED FROM THE MAIN SYSTEM AT UNIT 1
The emergency shut down system was activated at Unit 1. Three main circulating pumps were disconnected from the main system due to a failure of the power supply of the transducers. Serhiy Nazarenko, an official with the State Committee for Atomic Energy Use, stated that there was no increase in radiation levels in the area and the cause of the accident was being investigated. The reactor was to be shut down in the near future for repairs and regular maintenance of the control and safety mechanisms.
["Reactor at Khmelnytskyy Nuclear Plant Shut Down After Mishap," OMRI Daily Digest, Vol. 1, No. 12, 1/17/95.]
 
1/12/95: THE MOST COST-EFFICIENT WAY TO ADD GENERATING CAPACITY IS TO COMPLETE KHMELNYTSKYY
Westinghouse and its three partners (Italian firms Ansaldo and Fiat, and the Ukrainian Kyivatomenergoproekt) have come to the conclusion that the completion of Units 2, 3, and 4 at Khmelnytskyy , with the necessary Western safety upgrades, would be the most cost-efficient way to add to Ukraine's electricity generating capacity. Unit 2 is 85 percent complete, Unit 3 is 50 percent complete, and construction of Unit 4 has just begun. Westinghouse refuses to publicize the actual costs involved, stating that the price is a matter of controversy in Ukraine currently.
[Ann MacLachlan, "Upgrading, Finishing Three PWRs At Khmelnytskyy Is Cheapest Choice," Nucleonics Week, 1/12/95, pp. 13-14.]
 
12/12/94: NUCLEAR POWER TRAINING FACILITY WILL BE BUILT AT KHMELNYTSKYY
The United States has provided Ukraine with an $8.5 million grant to build a nuclear power training facility at Khmelnytskyy ; this is under the auspices of a 1992 agreement to transfer US experience to Ukraine. A full-scale computer based training facility will be built complete with simulators to complement an educational program. The training will concentrate on five areas: reactor control, turbine control, refueling operation, and instrumentation and control. Seven more specialties will be added later.
["Nuclear Training Boost for Ukraine," Nucnet, No. 590-591, 12/12/94.]
 
7/19/94: TWO INCIDENTS IN THREE DAYS AT UNIT 1
Due to a problem with the pipeline system, the output capacity of Unit 1 was reduced drastically. Following a reduction in energy load on the reactor, operators were able to solve the problem and restore output capacity to a normal level on the same day. Officials noted that accident safety norms were followed during and after the incident. Two days later, another incident occurred, involving a shutoff signal for Unit 1; this signal was given erroneously, however, during tests at the station. This problem was solved during the following two days.[1,2]
Sources:
[1] "Nuke Plant Malfunction Causes Scare," Intelnews, 7/94.
[2] Krymskaya Pravda, 7/26/94, p. 2; in "Incident At Khmelnytskyy AES Reported," FBIS-SOV-94-147, 8/1/94, p. 44.
 
3/8-19/93: SIX SAFETY PROBLEMS AT KHMELNYTSKYY
An IAEA Mission identified six major safety problems at the Khmelnytskyy NPP: fouling of heat exchangers in the emergency core cooling system, secondary circuit chemistry problems, diesel generator failures, degradation of safety functions owing to circuit breaker failures, deficiencies in maintenance procedures and acceptance criteria after maintenance, and common cause failures owing to deficiencies in instrumentation and control and electrical equipment.
[Source Book: Soviet-Designed Nuclear Power Plants in Russia, Ukraine, Lithuania, Armenia, the Czech Republic, the Slovak Republic, Hungary, and Bulgaria, 1996, pp. 148-49.]

 

Page last updated 4 June 2002
This file is no longer being updated.  For information on developments in the nuclear power industry, please see the Ukraine: General Nuclear Power Developments section.

Comments or questions? Contact Michael Jasinski at MIIS CNS: Michael.Jasinski@miis.edu

CNSThis material is produced independently for NTI by the Center for Nonproliferation Studies at the Monterey Institute of International Studies and does not necessarily reflect the opinions of and has not been independently verified by NTI or its directors, officers, employees, agents. Copyright © 2002 by MIIS.

HOME  |  CONTACT US  |  SITE MAP