Reducing Excess Stockpiles

US Plutonium Disposition
Status
![]() Reactor fuel pellets made from U.S. excess weapons plutonium. |
After years of studies and preparation and a brush with possible termination or fundamental redirection in the early days of the Bush administration the U.S. plutonium disposition program now appears to be poised to move forward. Construction of a facility to fabricate excess weapons plutonium into fuel for commercial nuclear power plants is slated to begin in 2004, and 34 tons of excess plutonium is scheduled to be burned as reactor fuel from 2008-2019.[1] A number of challenges for the effort remain, however. |
Program mission and purposes. With the end of the Cold War, the United States has declared that 52.5 tons of its stockpile of roughly 99.5 tons of plutonium is excess to its military needs.[2] The mission of the U.S. plutonium disposition program is to reduce, and eventually eliminate, this excess plutonium stockpile, for three reasons:
-
to make it possible to work with Russia to reduce Russia's huge excess plutonium stockpile in parallel;
-
to send a message to the world that U.S. nuclear arms reductions are intended to be permanent, not temporary;[3] and
-
to rationalize management of plutonium within the U.S. weapons complex, making it possible to close some plutonium facilities and reduce long-term plutonium storage and security costs.[4]
Background and history. As the Cold War came to an end and the United States began dismantling thousands of nuclear weapons, the question of what to do with the excess plutonium from dismantled weapons came to the fore. Unlike highly enriched uranium (HEU), the proliferation risks posed by weapons plutonium cannot be eliminated by simply blending the plutonium with other plutonium, as nearly all combinations of plutonium isotopes can be used in nuclear weapons; plutonium mixed with uranium can be separated back out again using unclassified chemical processes.[5] Moreover, because of the safety and security hazards plutonium poses, making reactor fuel from plutonium is more expensive than the fuel is worth, even if the plutonium itself is free and so disposition of excess plutonium will inevitably require a substantial subsidy.[6] In that sense, excess plutonium is a dangerous liability, not an asset.
In 1992, then-National Security Advisor Brent Scowcroft asked a committee of the National Academy of Sciences (NAS) to examine the options for dealing with excess plutonium. In September 1993, President Clinton issued a directive outlining his nonproliferation policies, which initiated an interagency (and international) examination of the options for dealing with excess weapons plutonium.
The NAS study, released in January 1994, outlined a comprehensive strategy for managing excess weapons-usable nuclear materials.[7] The study concluded that the appropriate objective for disposition of excess plutonium was to transform it into forms that would be "roughly as inaccessible for weapons use as the much larger and growing quantity of plutonium that exists in spent fuel from commercial reactors" the "spent fuel standard." The study argued that options should be chosen that could meet this objective as quickly as possible (minimizing the security hazards of prolonged storage), while maintaining stringent standards of security and accounting for the material throughout, and meeting all applicable safety and environmental standards. After examining a wide range of options, from shooting the excess plutonium into space to diluting it in the world's oceans, the study concluded that, while all options had disadvantages, the two most promising approaches were to use the plutonium as a plutonium-uranium mixed oxide (MOX) fuel in nuclear reactors that already existed, or to immobilize it with high-level wastes for eventual disposal. Both options would embed the plutonium in massive, intensely radioactive objects that would be very difficult to steal and to recover the plutonium from (spent fuel assemblies in the MOX option, logs of immobilized radioactive waste in the immobilization option); in both cases, these would have to be stored pending the eventual availability of a geologic repository. A companion volume released a year later recommended that, because there were risks of delay or failure on each of these tracks, both should be pursued.[8]
The Department of Energy's (DOEs) Office of Materials Disposition was established the day the NAS study was released and, working with an interagency working group on the subject, went through an extensive process of analyzing the options, taking into account costs, security benefits and hazards, and safety and environmental impacts. In the end, the Clinton administration decided to pursue a "dual-track" strategy, as the NAS studies had recommended, using some of the plutonium as reactor fuel and immobilizing the remainder with high-level wastes.[9]
Throughout the life of the effort, U.S. plutonium disposition and Russian plutonium disposition have been closely linked. From the beginning, Russia's Ministry of Atomic Energy (MINATOM), which sees plutonium fuel as central to the future of nuclear energy, insisted that whatever happened to U.S. plutonium, Russia's plutonium would be used as reactor fuel.[10] In the negotiations of the late 1990s, Russian negotiators objected to leaving open the option of the United States immobilizing most of its excess weapons plutonium while Russia used its stockpile as fuel, arguing (wrongly, in the author's view) that since immobilization would leave the plutonium weapon-grade (rather than degrading its isotopics to reactor-grade, as use in reactors would) the United States could readily recover plutonium from immobilized forms and rapidly rebuild a large weapons stockpile. Thus, the 2000 Plutonium Management and Disposition Agreement required that the United States use the MOX approach for at least 25 tons of the 34 tons of plutonium covered by the agreement.[11] (This agreement covers only 34 tons of plutonium, not 50 tons the amount declared excess in Russia because only 34 tons of the U.S. excess stockpile is weapon-grade material in forms comparable to the material Russia has declared excess.) In effect, this meant that of the two tracks, MOX was essential and immobilization was not.
By the end of the Clinton administration, the cost of the full dual-track plan, originally estimated in the range of $2 billion,[12] had ballooned to over $6 billion.[13] The Bush administration came to office deeply skeptical of the effort, openly asking whether American plutonium stockpiles posed a security risk worth spending billions of dollars to address. During much of 2001, as the Bush administration performed a review of all threat reduction programs with Russia, it appeared very likely that the U.S. plutonium disposition effort would be terminated or fundamentally redirected to focus on joint U.S.-Russian R&D on advanced plutonium-burning fuel cycles for the future of nuclear energy. But as the review progressed, it became clear that continuing the U.S. plutonium disposition effort was central to saving money and fulfilling commitments to clean up and close facilities within DOE's own complex. DOE planned to send all the plutonium from sites such as Rocky Flats to Savannah River, in South Carolina, and close Rocky Flats down, saving hundreds of millions of dollars a year but South Carolina would not allow the plutonium to be shipped there without a firm plan for what would be done with it, that involved jobs in South Carolina, and a plan for eventually shipping the material away to a permanent nuclear waste repository.[14] But at the same time, DOE had made a commitment to Colorado to get the plutonium out of Rocky Flats. In short, ending the plutonium disposition program would cost more than implementing it.
In the end, after an extensive re-screening of the full range of possible options, the Bush administration settled on a streamlined version of the previous plan, dropping immobilization and instead burning all 34 tons of plutonium covered by the U.S.-Russian agreement as MOX fuel.[15]
Current plans. The revised plutonium disposition plan calls for building both a MOX fuel fabrication plant and a separate plant to convert plutonium metal weapons components, or "pits," to oxide suitable for fuel fabrication at the Savannah River Site in South Carolina. Once fabricated into fuel, the plutonium would be used in 6-8 nuclear power plants (some of which are still to be identified).[16] A consortium of Duke, Cogema, and Stone & Webster (DCS) has been contracted to build and operate the MOX Fuel Fabrication Facility (MOX FFF) and irradiate the fabricated fuel. Under current plans, construction of the MOX FFF would begin in 2004, and the plant would begin operation in 2008, continuing until 2019.[17] Construction of the Pit Disassembly and Conversion Facility (PDCF) would begin later, since the MOX plant can begin by fabricating fuel from plutonium oxides that are already available. All told, the revised program is expected to cost $3.84 billion (in constant FY 2001 dollars)[18] roughly $113 million per ton of plutonium reduced. The administration has committed to the full five-year funding profile required to build these major facilities.
Remaining challenges. While DOE appears to be poised to move forward with plutonium disposition at last, important challenges remain and DOE's dismal record of success in bringing major projects to fruition on time and on budget in recent years suggests caution. Some of the remaining challenges include:
-
Linkage to Russian plutonium disposition. Congress has mandated that U.S. plutonium disposition only proceed if Russian plutonium disposition proceeds in parallel. Thus, for the U.S. program to move forward the Russian program has to move forward, and that is currently proving to be the greater challenge. (See Russian plutonium disposition.)
-
MOX political, technical, and licensing hurdles. A broad spectrum of grass-roots environmental and nonproliferation groups oppose the MOX plan, and will do everything they can to stop it.[19] Critics have attacked the MOX program as unsafe and likely to create new proliferation hazards, and they will have the opportunity to make their case as licensing proceedings move forward before the Nuclear Regulatory Commission (NRC). (See discussion of the MOX/immobilization controversy, below.) To gain regulatory and political approval, the program will have to ensure that they have designed the effort to avoid any substantial increase in safety or security risks as a result of the use of MOX. It remains conceivable that this opposition could stop the effort, particularly if there were a major accident or incident with fabrication or handling of MOX within the program or elsewhere in the world.
-
Convincing sufficient reactors to take part. The new approach will require more U.S. reactors to burn MOX fuel. The last effort to identify utilities interested in burning MOX fuel (in return for discounted fuel prices from a DOE subsidy) found very few who wanted to take on the challenge. Since reliable, stable fuel supplies are crucially important to utilities, tying themselves to a program whose fate hinges on the fate of Russian plutonium disposition may be particularly problematic from some utility managers' perspectives. Convincing enough reactors to burn this fuel may turn out to be a significant challenge especially given the inevitable opposition from non-government organizations at each site where the plutonium fuel will be burned.
-
Dealing with the other excess plutonium. The reason that previous plans had called for immobilizing more than 8 tons of the material covered under the U.S.-Russian agreement is that this material is contaminated with various chemicals that complicate its use as reactor fuel. Hence, under the new plan, the MOX plant would be equipped an expanded purification capability, to purify this material. Nevertheless, 2 tons of the material was judged as of early 2002 to be too contaminated to clean up for use as fuel, and was slated for disposal as waste.[20] Since DOE is legislatively barred from disposing of this material at the Waste Isolation Pilot Plant (WIPP) in New Mexico, its ultimate fate remains unclear. Similarly, the Office of Fissile Materials Disposition is no longer responsible for the 18.5 metric tons of U.S. excess plutonium (most of it in forms unsuitable for use as fuel) that is not covered by the 34-ton U.S.-Russian agreement. This material has been transferred to DOE's Office of Environmental Management, and its fate remains undecided.[21] Depending on the costs of managing these materials, it may be that the revised plan will not, in fact, turn out to be less costly overall than the previous plan.
-
Maintaining budgetary support and momentum. To move from studies to building facilities has required a very large increase in the plutonium disposition budget, which is scheduled to keep going up and to stay high for several more years. The administration has formally committed to the full five-year budget profile, and the program currently has good support in Congress but if a perception arises that momentum is again lagging and the program is not moving forward, support for these large budgets could be jeopardized.
The MOX/immobilization controversy. For decades, the United States has not pursued reprocessing of its spent nuclear fuel and recycling of the resulting plutonium, in part because of the proliferation hazards associated with large-scale use of separated plutonium as civilian fuel. Thus, critics argued that the decision to use excess weapons plutonium as fuel represented a reversal of this policy, and voiced concern that it could lead to increases in the use of plutonium fuel in other countries. For both supporters and opponents of plutonium recycling, the issue of what to do with weapons plutonium has become part of that long-term ideological struggle; other analysts have pointed that since the amount of excess weapons plutonium is large in terms of the number of bombs that could be made from it, but tiny in terms of the world's energy future, decisions on what to do about the security hazard posed by excess weapons plutonium can and should be made independently of the ongoing debate over the future of the civilian nuclear fuel cycle.[22]
Critics of MOX have generally supported immobilization as a better alternative. In an immobilization approach, the plutonium would be prepared for disposal by mixing it with high-level wastes (HLW) from past reprocessing (so as to create a radiation barrier roughly comparable to that from spent fuel), and putting it in a glass or ceramic matrix that would be stable enough to permit permanent disposal in a geologic repository. To avoid some of the technical difficulties that were expected to arise from mixing plutonium directly with HLW, DOE developed an approach known as "can-in-canister," in which the plutonium would be immobilized in ceramic "pucks," which would be placed in metal cans arrayed inside the large canisters into which molten glass containing HLW is poured.[23] MOX critics have argued that such an immobilization approach would be:
-
Cheaper. Immobilization advocates have generally argued that it would be cheaper to implement than the MOX approach, even when the value of the nuclear fuel produced in the MOX approach is taken into account.[24] DOE agrees that an all-immobilization approach would have been at least somewhat cheaper than the all-MOX approach chosen.[25]
-
Safer. MOX critics have argued that the use of MOX fuel will make reactors more difficult to control, reducing safety margins;[26] that the increase in the quantity of actinides in the core would result in more deaths in the event of a catastrophic reactor meltdown and containment failure;[27] that the ice-condenser containments used in the plants slated to use MOX are particularly vulnerable to such an accident;[28] and that immobilization would not run these safety risks. DOE has not provided a point-by-point rebuttal of these critiques, but its environmental impact analyses have concluded that there would be few significant safety issues associated with the use of such MOX.[29]
-
More secure. MOX critics have argued that the process of MOX fabrication is difficult to safeguard, and that transporting plutonium in fresh MOX fuel from fabrication plants to reactors could create serious security risks. Immobilization, they argue, would avoid the transportation risks. DOE has argued, by contrast, that with sufficient investment in security the security risks from transportation can be reduced to a low level (indeed, the MOX fuel is to be transported within the United States using the same Safe, Secure Transports (SSTs) used to transport nuclear weapons), and that difficulties of safeguarding MOX fabrication and future immobilization processes are roughly comparable.[30]
-
Faster. MOX critics also argue that since the capacity of an immobilization plant would not be limited by the number of reactors available to burn fuel, immobilization of a large stockpile of excess plutonium could be accomplished much more rapidly than MOX use could.[31] DOE, by contrast, argues that both would take about the same amount of time, with immobilization likely starting later because it is less fully technically developed.[32]
MOX advocates have their own set of critiques of immobilization, arguing that (a) because plutonium has never been immobilized on an industrial scale, the technical uncertainties and potential for delays on the immobilization track are substantially higher; and (b) because the plutonium is not irradiated and remains weapons-grade, it could be recovered for weapons use more easily. Most important, MOX advocates (including the Bush administration) point out that Russian negotiators had made it clear that Russia would not be willing to move forward with disposition of its own plutonium if all the U.S. excess plutonium were going to be immobilized, leaving it in a form from which Russian experts argue it could be readily recovered. As the current head of the U.S. disposition program put it: "It is not a question of MOX or immobilization. It is a question of MOX and Russian disposition, or immobilization and no Russian disposition at all."[33] Some independent analysts, including the author, remain of the view that both approaches have advantages and disadvantages, and that implementation of both should have been continued.
Advanced reactors and fuel cycles. Since the plutonium disposition debate began, advocates of a wide range of advanced reactor designs or advanced fuel cycle approaches have argued that their proposed system would offer the best solution for plutonium disposition. In recent years, advocates of the Gas-Turbine Modular Helium Reactor (GT-MHR) and of thorium-plutonium-uranium fuel cycles have been particularly active, and Congress has directed the Office of Fissile Materials Disposition to support limited research on some of these concepts. As virtually every government or independent analysis has concluded, however, paying and waiting for the development, licensing, and deployment of such new reactor or fuel cycle would result in substantial additional delays and higher costs, compared to beginning with the reactors that already exist and fuel cycle approaches that are already demonstrated.[34] If, however, such new approaches are developed and deployed as beneficial approaches to the future of nuclear energy, then their use to consume whatever excess plutonium still exists at that time should certainly be considered.
![]()
Budget
See
budget table
Through FY 2003, $1.179 billion has been appropriated for the U.S. plutonium disposition program. Because the program is moving from studies to actual construction, the budget is increasing substantially. The administration has requested $70.1 million for U.S. plutonium disposition, $415.6 million for construction of U.S. plutonium disposition facilities for FY 2004, and $24.7 million for various supporting activities an increase of hundreds of millions of dollars over the FY 2003 appropriation.[35] The administration has committed to request the full funding required to build the plutonium disposition facilities: as of early 2002, the projected request for U.S. plutonium disposition in FY 2005 was $485 million; in FY 2006, $565 million; in FY 2007, $513 million; and in FY 2008, $324 million, as construction of the facilities neared completion (all in FY 2001 dollars).[36]
![]()
Key Issues and Recommendations
Maintaining momentum. Plutonium disposition is in the unusual position of being a long-term project requiring urgent action. To maintain congressional support, it is crucial to move as quickly as possible toward construction and operation of the needed facilities for plutonium disposition. If the current momentum is lost, it may be very difficult to regain.
- Recommendation: The U.S. government should continue to place substantial priority on moving forward with disposition of U.S. excess plutonium, including providing the necessary funding and the high-level political support needed to overcome obstacles as they arise.
- Recommendation: The U.S. government should continue to seek to move the Russian disposition program forward as rapidly as practicable, so as to be able to move forward with the U.S. program.
Lack of a backup to MOX. There remain significant political and regulatory uncertainties on the MOX track. A significant accident or security incident involving plutonium fuel anywhere in the world, for example, could make the MOX program politically difficult to sustain.
- Recommendation: DOE should restart an immobilization research, development, and demonstration program, to ensure that the technology will be ready if needed.
- Recommendation: The U.S. government should work with Russian experts to analyze the difficulty and expense of recovering plutonium from immobilized forms for use in weapons, as part of a broader effort to convince Russian negotiators that immobilization is as viable a strategy for disposition of U.S. excess plutonium as use in reactor fuel.
Lack of a defined path forward for the excess plutonium not covered by the U.S.-Russian agreement. Most of this additional excess plutonium is not suitable for use as MOX fuel, or for direct disposal as waste without processing. While disposition of this plutonium is not directly linked to disposition of Russian plutonium, it is nonetheless important for sending a signal to the world that U.S. arms reductions are intended to be permanent, and for rationalizing management of plutonium in the U.S. complex.
- Recommendation: DOE should move forward in selecting a disposition path for this 18.5 tons of excess plutonium (as well as for the 2 tons of plutonium within the 34 tons covered by the U.S.-Russian agreement that is not suitable for use as MOX), and should consider the immobilization technology previous developed in the disposition program.
Large remaining military plutonium stockpiles. The plutonium stockpile that the United States has not declared excess is enough to support a stockpile of well over 10,000 nuclear weapons. Reductions in these stockpiles need to go far deeper than either the United States or Russia presently plan, if the goals of substantially reducing theft risks and ensuring the irreversibility of deep reductions in nuclear arms are to be achieved.
- Recommendation: The United States and Russia should work toward putting in place agreements to reduce their total stockpiles of nuclear warheads not just those deployed on active strategic systems to low levels, and to reduce their fissile material stockpiles to the levels necessary to support the agreed remaining number of warheads.
![]()
Links
| Key Resources | |
| U.S. National Academy of Sciences, Committee on International Security and Arms Control, Management and Disposition of Excess Weapons Plutonium (Washington, D.C.: National Academy Press, 1994). | |
| While now almost a decade old, this report continues to provide an excellent introduction to the management of excess stockpiles of plutonium and HEU, as well as a variety of aspects of securing stockpiles and building a transparency and monitoring regime for warheads and fissile materials. This report outlined many of the key criteria that are still being used to guide plutonium disposition programs (including the "spent fuel standard"), and called for further pursuit of two main approaches to disposition use of the plutonium as fuel in existing reactors, and mixing it with high-level wastes for immobilization and disposal. | |
| U.S. National Academy of Sciences, Committee on International Security and Arms Control, Management and Disposition of Excess Weapons Plutonium: Reactor-Related Options (Washington, D.C.: National Academy Press, 1995). | |
| This follow-up report provides more detail on specific reactor options for burning plutonium, and on the option of vitrifying excess plutonium with high-level reactor wastes. Given the uncertainties facing both the immobilization and reactor fuel approaches at that time, it recommended pursuing both approaches in parallel. | |
| U.S.-Russian Independent Scientific Commission on Disposition of Excess Weapons Plutonium: Final Report (Washington, D.C.: Office of Science and Technology Policy, June 1, 1997). | |
| This report, from a panel of distinguished U.S. and Russian nuclear experts co-chaired by John P. Holdren and Evgeniy P. Velikhov, recommended that both the United States and Russia pursue a dual-track disposition strategy using both MOX in existing reactors and immobilization, and made a range of other specific implementation recommendations for disposition of plutonium and nuclear stockpile transparency. | |
| Elena Sokova, Monterey Institute for International Studies, Center for Nonproliferation Studies, "Issues & Analysis: Plutonium Disposition," NTI Research Library: Issues & Analysis, June 2002 | |
| This issue brief from the NTI Research Library provides a useful summary of where plutonium disposition stood as of mid-2002, as well as a very useful list of relevant resources. | |
| Matthew
Bunn, "The Current Response: Disposition of U.S.
Fissile Material," in The Next Wave: Urgently
Needed New Steps to Control Warheads and Fissile Material (Washington, D.C.: Carnegie Endowment for International
Peace and Project on Managing the Atom, Harvard University,
2000), pp. 61-65. Download 141K PDF |
|
| This excerpt from a 2000 report discusses where the U.S. plutonium disposition program stood at that time. | |
| Nuclear Control Institute, "Plutonium Disposal." | |
| This page provides a large number of resources on the anti-MOX case, from the leading non-government organization providing technical critiques of MOX for plutonium disposition. | |
| Blue Ridge Defense League, "Southern Anti-Plutonium Campaign." | |
| Another page with a wide range of resources (click on news in particular) from well-informed non-government critics of the current plutonium disposition program. | |
| Duke, Cogema, Stone & Webster, Home Page. | |
| The web page for the consortium contracted to build the MOX plant and irradiate the fuel offers information on their plans, questions and answers, and more. | |
| United States Nuclear Regulatory Commission, MOX Fabrication Facility Licensing. | |
| This page from the Nuclear Regulatory Commission offers detailed information on the licensing process for the MOX fabrication facility. | |
| Allison Macfarlane and Adam Bernstein, "Canning Plutonium: Faster and Cheaper," Bulletin of the Atomic Scientists 55, no. 3 (May/June 1999). | |
| This article provides a good summary of the case for immobilization over MOX approaches to plutonium disposition. | |
| Allison Macfarlane, Frank von Hippel, Jungmin Kang, and Robert Nelson, "Plutonium Disposition: The Third Way," Bulletin of the Atomic Scientists 57, no. 3 (May/June 2001). | |
| This article outlines an approach, intended mainly for stockpiles of reactor-grade civilian plutonium, in which plutonium would be fabricated into rods that would be interspersed with spent fuel rods in canisters for disposal. | |
| Matthew Bunn and John P. Holdren, "Managing Military Uranium and Plutonium in the United States and the Former Soviet Union," Annual Review of Energy and Environment 22 (1997). | |
| This article provides a comprehensive look at U.S.-Russian programs to improve management of uranium and plutonium as they stood in 1997, with an in-depth discussion of excess plutonium disposition. | |
| Ed Lyman and Paul Leventhal, "Bury the Stuff," and John P. Holdren, "Work With Russia," Bulletin of the Atomic Scientists 53, no. 3 (March/April 1997). | |
| These articles provide a useful summary of the debate the dual-track decision provoked among non-government nonproliferation experts. | |
| Matthew Bunn, The Case for a Dual-Track Approach And How to Move Forward From Here, Nuclear Materials Monitor 1, no. 5 (June 14, 1997). [Originally presented to the conference on "Comprehensive Controls on Plutonium and Highly Enriched Uranium: Long-Term Problems and Prospects for Solutions," Institute for Science and International Security, Washington, D.C., 11 June 1997.] | |
| This article makes the case for the dual-track decision, and responds specifically to the key arguments raised by critics. | |
| U.S. General Accounting
Office, Nuclear Nonproliferation and Safety: Uncertainties
About the Implementation of U.S.-Russian Plutonium Disposition
Efforts, GAO/RCED-98-46 (Washington, D.C.: GAO,
January 14, 1998) Download 152K PDF |
|
| GAO expresses its concern at the time about the lack of a formal Russian commitment to dispose of its surplus plutonium in a manner reciprocal of the United States actions, and offers its doubts about the Russians wherewithal to finance such an operation. | |
| General Accounting Office, Department of Energy: Plutonium Needs, Costs,
and Management Programs, GAO/RCED-97-98 (Washington
D.C.: GAO, April 1997). Download 258K PDF |
|
| This GAO study makes clear that the cost of disposition of excess plutonium will in fact be just one small part of the overall future cost of managing the different plutonium stockpiles in the DOE complex. | |
| Agreements and Documents | |
| National Nuclear Security Administration, Office of Fissile Materials Disposition, Surplus Plutonium Disposition Program: Amended Record of Decision, Federal Register (April 19, 2002). | |
| This document officially confirms the modified all-MOX program announced by the Bush administration in early 2002. | |
| National Nuclear Security Administration, Office of Fissile Materials Disposition, Report to Congress: Disposition of Surplus Defense Plutonium at Savannah River Site (Washington, D.C.: NNSA, February 15, 2002). | |
| This report provides cost and schedule estimates for the all-MOX plan resulting from the Bush administration's review of the plutonium disposition program, and discusses other options that were considered. | |
| Agreement Between the Government of the United States of America and the Government of the Russian Federation Concerning the Management and Disposition of Plutonium Designated As No Longer Required for Defense Purposes and Related Cooperation, September 2, 2000. | |
| This agreement commits each side to carry out disposition of 34 tons of excess weapons plutonium, and provides for a range of specific implementation and monitoring measures. It requires that for the U.S. program, at least 25 tons of the 34 tons be used as reactor fuel, rather than being immobilized. (34 tons was chosen rather than the 50 tons in the earlier Presidential statement because only 34 tons of the U.S. excess is weapon-grade material comparable to the Russian excess material.) | |
| National Nuclear Security
Administration, Office of Defense Nuclear Nonproliferation, Office of Fissile Materials Disposition Strategic
Plan (Washington, D.C.: DOE, June, 2000). Download 842K PDF |
|
| This report outlines in detail the plans for the U.S. plutonium disposition program as they stood in mid-2000. | |
| Joint Statement of Principles For Management and Disposition of Plutonium Designated as No Longer Required for Defense Purposes, September 2, 1998 | |









