Russia Foreign Assistance CTR Destruction and Dismantlement ProgramsRussia: CTR Program Destruction and Dismantlement
Destruction and Dismantlement projects aim to eliminate all strategic
offensive weapons and infrastructure from Belarus, Kazakhstan, and Ukraine.
These projects assist Russia in keeping to the START I dismantlement timeframe
and also in establishing and implementing programs for the destruction
of its chemical weapons. For information on ICBM dismantlement, see the
Russia: Weapons: ICBM Deactivation
and Dismantlement file; for information on foreign assistance for submarine
dismantlement, see the Russia: Naval
Fuel Cycle Foreign Assistance section.[Department of Defense, "CTR
Destruction and Dismantlement: Forecast to Industry," 2/96, p. 2.] {Entered
10/27/96, mew} CHEMICAL WEAPONS DESTRUCTION This CTR chemical weapons (CW) destruction program has four
objectives: establishment of a chemical weapons destruction facility (CWDF) in
Shchuchye;
provision of chemical agent monitoring capabilities to support CW
elimination activities; conversion of Chemical
Weapons Production Facilities (CWPFs);
and CW
storage facility security enhancements. The project works
at two main locations: GosNIIOKhT (State Scientific Research Institute
for Organic Chemistry and Technology) Central Analytical Lab in Moscow,
and at the Shchuchye CWDF. The program’s objective is
to destroy 32,000t of chemical weapons.[1,2] The United States
and Russia signed an implementing agreement for chemical weapon destruction
on 30 July 1992 and then amended that agreement in March 1994 and May 1996.
By the end of 1996, the CTR program had provided up to $68 million for
chemical weapons destruction.[3] Through
FY2002, the United States had expended $208.59
million for CW
destruction projects in Russia ($39.42 in FY2002).[9]
On 18 May 1994, the US DoD awarded a $7.4
million contract to the Bechtel corporation for the development of a Comprehensive
Implementation Plan for destruction of Russian chemical munitions. Bechtel
produced a planning document for a destruction facility to be constructed
in Kurgan Oblast at Shchuchye. [3,4] In December 1996, Department of
Defense (DOD) contracted
with Parsons Engineering to design and construct the actual facility.[5]
As of January 2003, the construction schedule provided for initial
operations with live agents to commence in October 2007, and transfer to the Russian Federation in
March
2008.[9] The US funds
are to be used only for the building of the actual chemical destruction
facility. The Russian authorities must find resources to build the associated
infrastructure such as roads, water mains, and power, as well as one of the 100
buildings dedicated to destruction. Russia began work on the
support infrastructure in FY2000. DOD has started preparing the site, and as of
January 2003 was scheduled to
start construction of the main destruction building in April 2004. Although
the FY2002 National Defense Authorization Act removed the permanent
prohibition on construction, it replaced it with a requirement for certification by the
Secretary of Defense.[7] Conditions that Russia must fulfill in
order to receive certification include provision of comprehensive information on
the Russian CW stockpile; an annual commitment of $25 million in Russian funds to CW
elimination; development of a CW elimination plan; enactment of legislation
providing for elimination of all nerve agents at a single facility; an agreement to
eliminate CW production facilities in Volgograd and Novocheboksarsk, and a
demonstrated commitment from the international community to fund CW elimination
facility support infrastructure.[8]
The United States
originally wanted to build an incinerator to dispose of the chemical munitions,
but Russia believes this process to be environmentally unsound. Therefore
the CTR funds are going toward building a facility that employs Russian
neutralization technology.[6] The
Russian neutralization process was evaluated and approved by Bechtel National Inc.,
Battelle Memorial Institute, and GosNIIOKht.[7]
Under the Chemical Agent Analytical Monitoring project, CTR assistance is
provided for the establishment of a Central Chemical Weapons Destruction
Laboratory (which was dedicated in April 2000) at GosNIIOKhT and purchase
of three mobile analytical laboratories. The laboratory is to develop
of analytical methods and monitoring procedures for use at CW elimination
facilities. It will also assist in training elimination facility and mobile
laboratory personnel. The mobile laboratories will participate in operator
training and provide CW monitoring capabilities at CW storage sites and
elimination facilities.[7] They were provided in December 1996.[2]
Finally, the Chemical Weapons Site Security project provided $10 million through
FY2002 to improve security measures at the Shchuchye and Kizner CW storage
facilities. Completion of improvements at the Shchuchye facility is planned for
December 2002, and at the Kizner facility for March 2003. Logistical support
will be provided through FY2004.[7]
The CWPF Demilitarization project is intended to demilitarize nerve agent
production facilities at Khimprom (Volgograd) and its Plant No. 4 (Novocheboksarsk)
by decontaminating, dismantling, and destroying equipment used to produce,
transfer, and store chemical weapons and precursors. Although the Russian
government proposed two additional sites for CTR support, the Kaprolaktam
facility in Dzerzhinsk is instead receiving support from the European Union,
while the
Central Volga Chemical Factory in Chapayevsk was deemed an environmental
restoration project and is not receiving CTR assistance.[7]
Sources: [1] Department of Defense, "CTR
Program Implementation: Forecast to Industry, 23 February 1996. [2] Department of Defense, "CTR
Update: Russia," 19 September 1996. [3] "Background Document: The Cooperative
Threat Reduction Assistance to Russia", 16 January 1997, as found on the
website of the Stimson Center's Nuclear Roundtable, http://www.stimson.org/rd-table/ctr-russ.htm. [4] Theresa Hitchens and Stephen
C. LeSueur, "Critics Fear Misuse of U.S. Aid to Destroy Russian Arms",
Defense News, 3 July 1994, p. 14. [5] Franklin C. Miller, Assistant
Secretary of Defense for International Security Policy (Acting), Statement
for the Record before the Subcommittee on Strategic Forces, Senate Armed
Services Committee, 5 March 1997. [6] "Interview: A Look Forward...Cooperative
Threat Reduction Director Laura Holgate," Post-Soviet Nuclear &
Defense Monitor, 7 April 1997, p. 9. [7] "Cooperative Threat Reduction Annual
Report to Congress, Fiscal Year 2002."
[8] National Defense Authorization Act for Fiscal Year 2002, Sec. 1203, Library
of Congress Web Site, http://thomas.loc.gov/.{Updated 4/2/98 PBI}{Updated
8/29/2002 MJ}
[9] "Cooperative Threat Reduction Annual Report to Congress, Fiscal Year 2004,"
http://armedservices.house.gov/reports/2003exereports/03-01-01ctr.pdf.
ARCHIVED CHEMICAL WEAPONS DESTRUCTION DEVELOPMENTS:
This section is no longer being updated. For more recent developments, please see the
Foreign Assistance Programs developments file, as
well as the Chemical and Biological Weapons & WMD Terrorism News Archive, available online at
http://www.nti.org/db/cbw/index.htm.
9/27/96: GAO REPORT: DELAY FUNDS UNTIL ESTIMATE MADE The US General Accounting Office recommended in its September 1996 review
of the CTR program that Congress delay obligation of funds for the proposed
chemical weapons destruction facility in Shchuchye until the US Department
of Defense (DoD) provides a reliable estimate of the facility’s total cost
based upon a one-third completed design. (The DoD’s 1995 estimate of $900
million is considered outdated.) The report also recommended that the US
find out its exact share of the total cost. The DoD concurred with these
suggestions.
[GAO, "Weapons of Mass Destruction," GAO/NSIAD-96-222, 9/27/96.]{Entered,
2/11/97, mew} {Cleared 3/19/97 JWRL} 8/96: MOBILE LABORATORIES DELIVERED The project for chemical weapons destruction completed its joint technical
evaluation, and three mobile laboratories were delivered to Moscow in August
1996. The contract for construction of the pilot chemical weapons destruction
facility in Shchuchye is scheduled to awarded in December 1996 and construction
will begin in the first quarter of FY 97.
[Department of Defense, "CTR Update: Russia," 9/19/96.]{Entered
11/1/96, mew}
STRATEGIC OFFENSIVE ARMS ELIMINATION
(SOAE) Assistance in the area of strategic offensive
arms elimination provides Russia with the initial training of personnel
to operate equipment, one year of parts and maintenance, and consultation
for the destruction of Russia's strategic nuclear delivery vehicles
and facilities. Equipment in this category includes incinerators
to destroy liquid rocket fuel and oxidizer derived from weapons destruction,
cranes to help prepare missile silos for dismantlement, plasma cutters
to cut up missile and heavy bomber airframes, and hydraulic shears to cut
up the hulls of nuclear submarines. At least $5 million in Cooperative
Threat Reduction (CTR) funds have also gone to build service roads for
access to missile silos and launchers being dismantled.[1] The US DOD and the Russian Ministry of Defense Industry signed an SOAE implementing
agreement on 26 August 1993 and the United States has been shipping SOAE
equipment to Russia since July 1994. [2]
The overall SOAE
elimination goals under the CTR program include deactivation of 13,300 strategic warheads,
elimination of 1,473 ICBMs, 936
SLBMs, 713 nuclear cruise
missiles, and 205 bombers. Infrastructure subject to elimination includes 831
ICBM silos, 442 mobile ICBM launchers, 48 SSBNs
with 728 SLBM
launchers, and 194 nuclear test tunnels and shafts.[6] As of spring 1996, CTR assistance
had helped eliminate more than 200 SLBM launchers, more than 350 ICBM silos,
more than 1,300 ballistic missiles, 25 heavy bombers, and had removed more
than 1,000 strategic nuclear warheads from deployed delivery systems. These
CTR funds helped Russia become the only nuclear weapon successor state
of the Soviet Union and also helped Russia fulfill its START I treaty obligations.[3] By
July 2002 the total had increased to 5,970 deactivated warheads, 464 destroyed
ICBMs, 322 destroyed SLBMs,
97 destroyed bombers, and 483 destroyed cruise missiles. Progress was also
being made in the area of infrastructure elimination, with the number of
eliminated ICBM silos increasing to 432 and SSBNs
to 24 (with 396 SLBM
launchers). While only one mobile ICBM launcher had eliminated by July 2002,
the task of sealing nuclear test tunnels and shafts was fully completed. The
goal of eliminating nuclear cruise missiles is to be completed by the end of
2004, but other elimination activities will proceed through 2007 and beyond.[6]
SOAE activities have been broken up into a number of discrete projects.
The Solid Propellant Disposition Facility (SPDF) was intended to provide the
Russian Federation with a contained incineration system to remove propellant
from solid-fuel ICBMs and SLBMs and to cut up missile bodies and canisters in
accordance with START I elimination requirements. Although $99 million had been
spent by FY2000, as of 2002 SPDF had not entered operation. Delays have been
caused by the need to conduct additional equipment tests and the resistance of
local Russian governments.[7] In February 2002 the government of Udmurtiya
rejected a plan to locate the SPDF in the city of Votkinsk.[8]
The Solid Propellant ICBM/SLBM and Mobile Launcher Elimination project is aimed
at eliminating SS-24 and SS-25 ICBMs, and SS-N-20 SLBMs. This project entails
repairs to Russian missile disassembly facilities, fitting out and operating
mobile launcher elimination facilities, elimination of SLBMs
through open-air burning, and other activities.[7] Preparations for elimination
of SS-24 rail-mobile launchers began in December 2001 at the 85th Repair
Plant in Bryansk,[9] and the elimination of SS-25 road-mobile launchers is
planned to commence in FY2003.[7] Since that time, the number of SS-25 missiles
to be eliminated has been increased by 173 in 2002,
and the number of road mobile SS-25 launchers by 102, and the program extended
through FY2009.[12]
The
Emergency Response Support Equipment portion of the SOAE effort included the
provision of equipment to be used in the event of an accident during
transportation of ballistic missiles or liquid rocket fuel. The emergency
response train provided includes a rail-mounted crane, hydraulic tools,
hydro-abrasive cutters, concrete pulverizers, and an excavator. It is based in
Krasnoyarsk. Raytheon Technical Services Company and
Parsons Delaware, Inc., are
providing technical support, which will continue until ICBM and SLBM elimination
activities are completed. Total funding for this project reached $7.5 million by
FY2000, and will continue at a rate of $200,000 a year through FY2007.[7]
The Liquid Propellant Disposition Systems project was designed to assist the Russian Federation
in eliminating the highly toxic liquid fuel and oxidizer used in ballistic
missiles. The project included provision of unsymmetrical dimethyl hydrazine (UDMH)
disposition systems that break down the propellant into commercial chemicals,
intermodal containers, flatbed railcars, and cranes, and mobile oxidizer
processing systems (MOPS) to convert 43,000t of dinitrogen tetroxide oxidizer
into nitric acid. MOPS also has the capability to convert melange
oxidizer, an activity which was to be funded by the Russian government. Two UDMH
disposition systems were delivered to
Krasnoyarsk. US firms involved as contractors in UDMH
disposition project include Thiokol (integrating),
Honeywell,
Ware Energy, W&E
Logistics, McAbee Construction, and Omni Instrumentation. The contract to
develop MOPS was awarded to Bechtel International Services Inc.[7] However, delays in implementing this project
were cited as reasons for the Russian government to sell much
of the liquid fuel to International Launch Services Inc. for use in space
launches.[10] In February 2002 DOD learned that both fuel and oxidizer had been
diverted to the space program, and issued a stop work order on the liquid
propellant disposition contract.[12]
The Liquid Propellant ICBM and Silo Elimination project has the goal of
eliminating 87 SS-17 ICBMs, 206 SS-18 ICBMs and launch canisters, 73 SS-19 ICBMs
and launch canisters and 90 SS-18 launch silos. The DOD provided necessary
equipment (such as cranes, earth-moving equipment, scrap metal handling
equipment, and industrial tools) for the
Pibanshur,
Uzhur, Yedrovo,
Sechuga/Surovatikha,
and Perm/Bershet elimination bases. In addition, the SS-18 elimination facility
at Surovatikha is undergoing an upgrade, which was 60% complete as of January
2001. In FY 2000 Brown & Root Services Company was selected as the integrating
contractor for the project, and the Russian firm Rosobshchemash won the contract
to eliminate the first six SS-18 silos.[7] As of January 2003 the total cost of the
project was estimated at $337.8 million, with $217.8 appropriated through
FY2002.[12]
The
Liquid Propellant SLBM Elimination project assists the Russian Federation in the
elimination of SS-N-6, SS-N-8, and SS-N-18 SLBMs by defueling and transporting
the missiles to elimination facilities, and subsequently destroying the missiles.
Specific activities within the project included performing upgrades to
elimination facilities at the Scientific Research Institute of Chemical and
Construction Equipment (NIIKhSM) in Sergiyev Posad and the
Krasnoyarsk Machine-Building Plant (Krasmash),
and the Revda base where missiles are defueled. By 2001 DTRA had negotiated
contracts for the elimination of a total of 453 liquid-fuel SLBMs, including up
to 173 at NIIKhSM and up to 280 at Krasmash.[7] The total number of SLBMs to be
eliminated may increase to 642 if projected elimination of Delta III and one
Delta IV submarines takes place.[12] The contracts also include funding for upgrades
of defueling and neutralization equipment, railcar maintenance, rail
renovations, office equipment, and recertifications of renovated equipment.[7]
Through
FY2002 $36.4 million had been allocated for this project, and eventual costs are expected
to total $50.7 million.[12]
The
SLBM Launcher Elimination/SSBN Dismantlement project funds the elimination of
Russian SLBM launchers and associated SSBNs in accordance with START I
elimination protocols. Under this project, two Yankee-class, 36 Delta-class, and
five Typhoon-class are to be eliminated under direct contracts awarded to four
START-designated elimination facilities:
Zvedochka,
Sevmash (both in
Severodvinsk), Nerpa (Snezhnogorsk, near Murmansk), and
Zvezda (Bolshoy Kamen,
near Vladivostok). Contracts for 17 SSBNs were issued in FY1998 and FY1999.[7] As
of January 2003 the estimated cost of the program was estimated at
$434.8 million, and will continue beyond
FY2009.[12] However, it may decrease due to the Russian Navy's
apparent decision to retain up to three Typhoon-class SSBNs in service.[11] Also
please see the Naval Fuel Cycle
Foreign Assistance section for more information.
The Heavy Bomber Elimination Equipment project is complete, with equipment worth
$10.3 million having been provided to Russia.[7] Elimination activities
are continuing at the elimination facility at the
Engels air base.
By April 1997, according to then CTR Director Laura Holgate, almost $300 million was
being spent on strategic dismantlement work.
For FY 1998 DOD requested $210 million for strategic offensive arms elimination.
The amount of that sum to be spent in Russia was earmarked for the continuing
elimination programs in place for bombers, SS-18 missiles, SS-24 rail mobile
launchers, and submarine-launched ballistic missiles.[5] Through FY 2000 the total funding
allocated for SOAE activities had reached $729.9 million, and is expected to
rise to $1.6 billion by FY 2009.[7,12]
For more details on the elimination process please
see the database's sections on Russia's
nuclear weapons and Russia's
naval reactors.
Sources: [1] "Nunn-Lugar Contract," Eastern
Economist, 9 June 1997, vol. 4, no. 20, p. 12. [2] "Background Document: The Cooperative
Threat Reduction Assistance to Russia", 16 January 1997, as found on the
website of the Stimson Center's Nuclear Roundtable, http://www.stimson.org/rd-table/ctr-russ.htm. [3] William C. Potter and John
M. Shields, "Lessons from the Nunn-Lugar Cooperative Threat Reduction Program,"
Asia-Pacific Review, Spring/Summer 1997, vol. 4, no.1, p. 37. [4] "Interview: A Look Forward...Cooperative
Threat Reduction Director Laura Holgate," Post-Soviet Nuclear &
Defense Monitor, 7 April 1997, p. 6. [5] Franklin C. Miller, Assistant
Secretary of Defense for International Security Policy (Acting), Statement
for the Record before the Subcommittee on Strategic Forces, Senate Armed
Services Committee, 5 March 1997. [6] "Cooperative
Threat Reduction Scorecard," Defense Threat Reduction Agency Web Site,
http://www.dtra.mil/ctr/ctr_score.html, 18 July 2002.
[7] Cooperative Threat Reduction Annual
Report to Congress, Fiscal Year 2002.
[8] Mayak radio, 28 February 2002; in "Construction of Russian missile
scrapping plant vetoed by local authorities," FBIS Document CEP20020228000193.
[9] Vladimir Kravchenko, "Our
Missiles Sent for Scrap," Izvestiya online edition,
http://www.izvestia.ru, 28 December
2001; in "Bryansk Plant Prepares To Scrap Rail-Mobile Launchers," FBIS
Document DEP20020102000058.
[10] Guy Chazan, "U.S. Program Gets Burned In Deal To Convert
Russian Missile Fuel," The Wall Street Journal, 24 May 2002.
[11] Interfax, 4 July 2002; in "Russia: Three of six Shark
submarines to be cut up," FBIS Document CEP20020704000010. {Updated 4/2/98 PBI}{Updated 8/29/2002 MJ}
[12] "Cooperative Threat Reduction Annual Report to Congress, Fiscal Year 2004,"
http://armedservices.house.gov/reports/2003exereports/03-01-01ctr.pdf.
Page last updated 1 February 2005
Comments or questions? Contact Cristina Chuen at MIIS CNS: Cristina.ChuenATmiis.edu